§ 153A-320.  Territorial jurisdiction.

Each of the powers granted to counties by this Article and by Article 19 of Chapter 160A of the General Statutes may be exercised throughout the county except as otherwise provided in G.S. 160A-360.  (1959, c. 1006, s. 1; c. 1007; 1965, c. 194, s. 2; c. 195; 1969, c. 1066, s. 1; 1973, c. 822, s. 1; 2011-326, s. 9.)

 

§ 153A-320.1.  Permit choice.

If a rule or ordinance changes between the time a permit application is submitted and a permit decision is made, then G.S. 143-755 shall apply.  (2014-120, s. 16(b).)

 

§ 153A-321.  Planning boards.

A county may by ordinance create or designate one or more boards or commissions to perform the following duties:

(1)        Make studies of the county and surrounding areas;

(2)        Determine objectives to be sought in the development of the study area;

(3)        Prepare and adopt plans for achieving these objectives;

(4)        Develop and recommend policies, ordinances, administrative procedures, and other means for carrying out plans in a coordinated and efficient manner;

(5)        Advise the board of commissioners concerning the use and amendment of means for carrying out plans;

(6)        Exercise any functions in the administration and enforcement of various means for carrying out plans that the board of commissioners may direct;

(7)        Perform any other related duties that the board of commissioners may direct.

A board or commission created or designated pursuant to this section may include but shall not be limited to one or more of the following:

(1)        A planning board or commission of any size (with not fewer than three members) or composition considered appropriate, organized in any manner considered appropriate;

(2)        A joint planning board created by two or more local governments according to the procedures and provisions of Chapter 160A, Article 20, Part 1. (1945, c. 1040, s. 1; 1955, c. 1252; 1957, c. 947; 1959, c. 327, s. 1; c. 390; 1973, c. 822, s. 1; 1979, c. 611, s. 6; 1997-309, s. 5; 2004-199, s. 41(c).)

 

§ 153A-322.  Supplemental powers.

(a)        A county or its designated planning board may accept, receive, and disburse in furtherance of its functions funds, grants, and services made available by the federal government or its agencies, the State government or its agencies, any local government or its agencies, and private or civic sources. A county, or its designated planning board with the concurrence of the board of commissioners, may enter into and carry out contracts with the State or federal governments or any agencies of either under which financial or other planning assistance is made available to the county and may agree to and comply with any reasonable conditions that are imposed upon the assistance.

(b)        A county, or its designated planning board with the concurrence of the board of commissioners, may enter into and carry out contracts with any other county, city, regional council, or planning agency under which it agrees to furnish technical planning assistance to the other local government or planning agency. A county, or its designated planning board with the concurrence of the board of commissioners, may enter into and carry out contracts with any other county, city, regional council, or planning agency under which it agrees to pay the other local government or planning board for technical planning assistance.

(c)        A county may make any appropriations that may be necessary to carry out an activity or contract authorized by this Article, by Chapter 157A, or by Chapter 160A, Article 19 or to support, and compensate members of, any planning board that it may create or designate pursuant to this Article.

(d)       A county may elect to combine any of the ordinances authorized by this Article into a unified ordinance. Unless expressly provided otherwise, a county may apply any of the definitions and procedures authorized by law to any or all aspects of the unified ordinance and may employ any organizational structure, board, commission, or staffing arrangement authorized by law to any or all aspects of the ordinance. (1945, c. 1040, s. 1; 1955, c. 1252; 1957, c. 947; 1959, c. 327, s. 1; c. 390; 1973, c. 822, s. 1; 1983, c. 377, s. 8; 2004-199, s. 41(d); 2005-418, s. 1(b).)

 

§ 153A-323.  Procedure for adopting, amending, or repealing ordinances under this Article and Chapter 160A, Article 19.

(a)        Before adopting, amending, or repealing any ordinance authorized by this Article or Chapter 160A, Article 19, the board of commissioners shall hold a public hearing on the ordinance or amendment. The board shall cause notice of the hearing to be published once a week for two successive calendar weeks. The notice shall be published the first time not less than 10 days nor more than 25 days before the date fixed for the hearing. In computing such period, the day of publication is not to be included but the day of the hearing shall be included.

(b)        If the adoption or modification of the ordinance would result in any of the changes listed in this subsection and those changes would be located five miles or less from the perimeter boundary of a military base, the board of commissioners shall provide written notice of the proposed changes by certified mail, or by any other written means reasonably designed to provide actual notice, to the commander of the military base or the commander's designee not less than 10 days nor more than 25 days before the date fixed for the public hearing. Prior to the date of the public hearing, the military may provide comments or analysis to the board regarding the compatibility of the proposed changes with military operations at the base. If the board does not receive a response within 30 days of the notice, the military is deemed to waive the comment period. If the military provides comments or analysis regarding the compatibility of the proposed ordinance or amendment with military operations at the base, the board of commissioners shall take the comments and analysis into consideration before making a final determination on the ordinance. The proposed changes requiring notice are:

(1)        Changes to the zoning map.

(2)        Changes that affect the permitted uses of land.

(3)        Changes relating to telecommunications towers or windmills.

(4)        Changes to proposed new major subdivision preliminary plats.

(5)        An increase in the size of an approved subdivision by more than fifty percent (50%) of the subdivision's total land area including developed and undeveloped land.  (1959, c. 1006, s. 1; c. 1007; 1973, c. 822, s. 1; 1981, c. 891, ss. 2, 9; 2004-75, s. 1; 2005-426, s. 1(b); 2013-59, s. 1.)

 

§ 153A-324.  Enforcement of ordinances.

(a)        In addition to the enforcement provisions of this Article and subject to the provisions of the ordinance, any ordinance adopted pursuant to this Article, to Chapter 157A, or to Chapter 160A, Article 19 may be enforced by any remedy provided by G.S. 153A-123.

(b)        If the county is found to have illegally exacted a tax, fee, or monetary contribution for development or a development permit not specifically authorized by law, the county shall return the tax, fee, or monetary contribution plus interest of six percent (6%) per annum. (1959, c. 1006, s. 1; 1961, c. 414; 1973, c. 822, s. 1; 2007-371, s. 1.)

 

§ 153A-325.  Submission of statement concerning improvements.

A county may by ordinance require that when a property owner improves property at a cost of more than twenty-five hundred dollars ($2,500) but less than five thousand dollars ($5,000), the property owner must, within 14 days after the completion of the work, submit to the county assessor a statement setting forth the nature of the improvement and the total cost thereof. (1983, c. 614, s. 4; 1987, c. 45, s. 1.)

 

§ 153A-326.  Building setback lines.

Counties shall have the same authority to regulate building setback lines as is provided for cities in G.S. 160A-306. (1987, c. 747, s. 15.)

 

§ 153A-327.  Reserved for future codification purposes.

 

§ 153A-328.  Reserved for future codification purposes.

 

§ 153A-329.  Reserved for future codification purposes.

 

Part 2. Subdivision Regulation.

§ 153A-330.  Subdivision regulation.

A county may by ordinance regulate the subdivision of land within its territorial jurisdiction. If a county, pursuant to G.S. 153A-342, has adopted a zoning ordinance that applies only to one or more designated portions of its territorial jurisdiction, it may adopt subdivision regulations that apply only within the areas so zoned and need not regulate the subdivision of land in the rest of its jurisdiction. In addition to final plat approval, the ordinance may include provisions for review and approval of sketch plans and preliminary plats. The ordinance may provide for different review procedures for differing classes of subdivisions. The ordinance may be adopted as part of a unified development ordinance or as a separate subdivision ordinance. Decisions on approval or denial of preliminary or final plats may be made only on the basis of standards explicitly set forth in the subdivision or unified development ordinance. Whenever the ordinance includes criteria for decision that require application of judgment, those criteria must provide adequate guiding standards for the entity charged with plat approval. (1959, c. 1007; 1965, c. 195; 1973, c. 822, s. 1; 2005-418, s. 2(b).)

 

§ 153A-331.  Contents and requirements of ordinance.

(a)        A subdivision control ordinance may provide for the orderly growth and development of the county; for the coordination of transportation networks and utilities within proposed subdivisions with existing or planned streets and highways and with other public facilities; for the dedication or reservation of recreation areas serving residents of the immediate neighborhood within the subdivision and of rights-of-way or easements for street and utility purposes including the dedication of rights-of-way pursuant to G.S. 136-66.10 or G.S. 136-66.11; and for the distribution of population and traffic in a manner that will avoid congestion and overcrowding and will create conditions that substantially promote public health, safety, and the general welfare.

(b)        The ordinance may require that a plat be prepared, approved, and recorded pursuant to the provisions of the ordinance whenever any subdivision of land takes place. The ordinance may include requirements that the final plat show sufficient data to determine readily and reproduce accurately on the ground the location, bearing, and length of every street and alley line, lot line, easement boundary line, and other property boundaries, including the radius and other data for curved property lines, to an appropriate accuracy and in conformity with good surveying practice.

(c)        A subdivision control ordinance may provide that a developer may provide funds to the county whereby the county may acquire recreational land or areas to serve the development or subdivision, including the purchase of land that may be used to serve more than one subdivision or development within the immediate area.

(d)       The ordinance may provide that in lieu of required street construction, a developer may provide funds to be used for the development of roads to serve the occupants, residents, or invitees of the subdivision or development. All funds received by the county under this section shall be transferred to the municipality to be used solely for the development of roads, including design, land acquisition, and construction. Any municipality receiving funds from a county under this section is authorized to expend such funds outside its corporate limits for the purposes specified in the agreement between the municipality and the county. Any formula adopted to determine the amount of funds the developer is to pay in lieu of required street construction shall be based on the trips generated from the subdivision or development. The ordinance may require a combination of partial payment of funds and partial dedication of constructed streets when the governing body of the county determines that a combination is in the best interest of the citizens of the area to be served.

(e)        The ordinance may provide for the more orderly development of subdivisions by requiring the construction of community service facilities in accordance with county plans, policies, and standards. To assure compliance with these and other ordinance requirements, the ordinance may provide for performance guarantees to assure successful completion of required improvements at the time the plat is recorded as provided in subsection (b) of this section. For any specific development, the type of performance guarantee from the range specified by the county shall be at the election of the developer.

(f)        The ordinance may provide for the reservation of school sites in accordance with comprehensive land use plans approved by the board of commissioners or the planning board. For the authorization to reserve school sites to be effective, the board of commissioners or planning board, before approving a comprehensive land use plan, shall determine jointly with the board of education with jurisdiction over the area the specific location and size of each school site to be reserved, and this information shall appear in the plan. Whenever a subdivision that includes part or all of a school site to be reserved under the plan is submitted for approval, the board of commissioners or the planning board shall immediately notify the board of education. The board of education shall promptly decide whether it still wishes the site to be reserved and shall notify the board of commissioners or planning board of its decision. If the board of education does not wish the site to be reserved, no site may be reserved. If the board of education does wish the site to be reserved, the subdivision may not be approved without the reservation. The board of education must acquire the site within 18 months after the date the site is reserved, either by purchase or by exercise of the power of eminent domain. If the board of education has not purchased the site or begun proceedings to condemn the site within the 18 months, the subdivider may treat the land as freed of the reservation.

(g)        Any performance guarantee shall comply with G.S. 160A-372(g).  (1959, c. 1007; 1973, c. 822, s. 1; 1975, c. 231; 1987, c. 747, ss. 10, 17; 2005-426, s. 2(b); 2015-187, s. 1(b).)

 

§ 153A-332.  Ordinance to contain procedure for plat approval; approval prerequisite to plat recordation; statement by owner.

A subdivision ordinance adopted pursuant to this Part shall contain provisions setting forth the procedures to be followed in granting or denying approval of a subdivision plat before its registration.

The ordinance shall provide that the following agencies be given an opportunity to make recommendations concerning an individual subdivision plat before the plat is approved:

(1)        The district highway engineer as to proposed State streets, State highways, and related drainage systems;

(2)        The county health director or local public utility, as appropriate, as to proposed water or sewerage systems;

(3)        Any other agency or official designated by the board of commissioners.

The ordinance may provide that final decisions on preliminary plats and final plats are to be made by:

(1)        The board of commissioners,

(2)        The board of commissioners on recommendation of a designated body, or

(3)        A designated planning board, technical review committee, or other designated body or staff person.

From the effective date of a subdivision ordinance that is adopted by the county, no subdivision plat of land within the county's jurisdiction may be filed or recorded until it has been submitted to and approved by the appropriate board or agency, as specified in the subdivision ordinance, and until this approval is entered in writing on the face of the plat by an authorized representative of the county. The Review Officer, pursuant to G.S. 47-30.2, shall not certify a plat of a subdivision of land located within the territorial jurisdiction of the county that has not been approved in accordance with these provisions, and the clerk of superior court may not order or direct the recording of a plat if the recording would be in conflict with this section. (1959, c. 1007; 1973, c. 822, s. 1; 1997-309, s. 6; 2005-418, s. 3(b).)

 

§ 153A-333.  Effect of plat approval on dedications.

The approval of a plat does not constitute or effect the acceptance by the county or the public of the dedication of any street or other ground, public utility line, or other public facility shown on the plat and shall not be construed to do so. (1959, c. 1007; 1973, c. 822, s. 1.)

 

§ 153A-334.  Penalties for transferring lots in unapproved subdivisions.

(a)        If a person who is the owner or the agent of the owner of any land located within the territorial jurisdiction of a county that has adopted a subdivision regulation ordinance subdivides his land in violation of the ordinance or transfers or sells land by reference to, exhibition of, or any other use of a plat showing a subdivision of the land before the plat has been properly approved under the ordinance and recorded in the office of the appropriate register of deeds, he is guilty of a Class 1 misdemeanor. The description by metes and bounds in the instrument of transfer or other document used in the process of selling or transferring land does not exempt the transaction from this penalty. The county may bring an action for injunction of any illegal subdivision, transfer, conveyance, or sale of land, and the court shall, upon appropriate findings, issue an injunction and order requiring the offending party to comply with the subdivision ordinance. Building permits required pursuant to G.S. 153A-357 may be denied for lots that have been illegally subdivided. In addition to other remedies, a county may institute any appropriate action or proceedings to prevent the unlawful subdivision of land, to restrain, correct, or abate the violation, or to prevent any illegal act or conduct.

(b)        The provisions of this section shall not prohibit any owner or its agent from entering into contracts to sell or lease by reference to an approved preliminary plat for which a final plat has not yet been properly approved under the subdivision ordinance or recorded with the register of deeds, provided the contract does all of the following:

(1)        Incorporates as an attachment a copy of the preliminary plat referenced in the contract and obligates the owner to deliver to the buyer a copy of the recorded plat prior to closing and conveyance.

(2)        Plainly and conspicuously notifies the prospective buyer or lessee that a final subdivision plat has not been approved or recorded at the time of the contract, that no governmental body will incur any obligation to the prospective buyer or lessee with respect to the approval of the final subdivision plat, that changes between the preliminary and final plats are possible, and that the contract or lease may be terminated without breach by the buyer or lessee if the final recorded plat differs in any material respect from the preliminary plat.

(3)        Provides that if the approved and recorded final plat does not differ in any material respect from the plat referred to in the contract, the buyer or lessee may not be required by the seller or lessor to close any earlier than five days after the delivery of a copy of the final recorded plat.

(4)        Provides that if the approved and recorded final plat differs in any material respect from the preliminary plat referred to in the contract, the buyer or lessee may not be required by the seller or lessor to close any earlier than 15 days after the delivery of the final recorded plat, during which 15-day period the buyer or lessee may terminate the contract without breach or any further obligation and may receive a refund of all earnest money or prepaid purchase price.

(c)        The provisions of this section shall not prohibit any owner or its agent from entering into contracts to sell or lease land by reference to an approved preliminary plat for which a final plat has not been properly approved under the subdivision ordinance or recorded with the register of deeds where the buyer or lessee is any person who has contracted to acquire or lease the land for the purpose of engaging in the business of construction of residential, commercial, or industrial buildings on the land, or for the purpose of resale or lease of the land to persons engaged in that kind of business, provided that no conveyance of that land may occur and no contract to lease it may become effective until after the final plat has been properly approved under the subdivision ordinance and recorded with the register of deeds. (1959, c. 1007; 1973, c. 822, s. 1; 1977, c. 820, s. 1; 1993, c. 539, s. 1063; 1994, Ex. Sess., c. 24, s. 14(c); 2005-426, s. 3(b).)

 

§ 153A-335.  "Subdivision" defined.

(a)        For purposes of this Part, "subdivision" means all divisions of a tract or parcel of land into two or more lots, building sites, or other divisions when any one or more of those divisions are created for the purpose of sale or building development (whether immediate or future) and includes all division of land involving the dedication of a new street or a change in existing streets; however, the following is not included within this definition and is not subject to any regulations enacted pursuant to this Part:

(1)        The combination or recombination of portions of previously subdivided and recorded lots if the total number of lots is not increased and the resultant lots are equal to or exceed the standards of the county as shown in its subdivision regulations.

(2)        The division of land into parcels greater than 10 acres if no street right-of-way dedication is involved.

(3)        The public acquisition by purchase of strips of land for widening or opening streets or for public transportation system corridors.

(4)        The division of a tract in single ownership the entire area of which is no greater than two acres into not more than three lots, if no street right-of-way dedication is involved and if the resultant lots are equal to or exceed the standards of the county as shown by its subdivision regulations.

(b)        A county may provide for expedited review of specified classes of subdivisions. (1959, c. 1007; 1973, c. 822, s. 1; 1979, c. 611, s. 2; 2003-284, s. 29.23(b); 2005-426, s. 4(b).)

 

§ 153A-336.  Appeals of decisions on subdivision plats.

(a)        When a subdivision ordinance adopted under this Part provides that the decision whether to approve or deny a preliminary or final subdivision plat is to be made by a board of commissioners or a planning board, other than a planning board comprised solely of members of a county planning staff, and the ordinance authorizes the board of commissioners or planning board to make a quasi-judicial decision in deciding whether to approve the subdivision plat, then that quasi-judicial decision of the board of commissioners or planning board shall be subject to review by the superior court by proceedings in the nature of certiorari. The provisions of G.S. 153A-340(f), 160A-388(e2)(2), and 153A-349 shall apply to those appeals.

(b)        When a subdivision ordinance adopted under this Part provides that a board of commissioners, planning board, or staff member is authorized to make only an administrative or ministerial decision in deciding whether to approve a preliminary or final subdivision plat, then any party aggrieved by that administrative or ministerial decision may seek to have the decision reviewed by filing an action in superior court seeking appropriate declaratory or equitable relief. Such an action must be filed within the time frame specified in G.S. 153A-340(f) for petitions in the nature of certiorari.

(c)        For purposes of this section, an ordinance shall be deemed to authorize a quasi-judicial decision if the board of commissioners or planning board is authorized to decide whether to approve or deny the plat based not only upon whether the application complies with the specific requirements set forth in the ordinance, but also on whether the application complies with one or more generally stated standards requiring a discretionary decision to be made by the board of commissioners or planning board.  (2009-421, s. 2(b); 2013-126, s. 7.)

 

§ 153A-337.  Reserved for future codification purposes.

 

§ 153A-338.  Reserved for future codification purposes.

 

§ 153A-339.  Reserved for future codification purposes.

 

Part 3. Zoning.

§ 153A-340.  Grant of power.

(a)        For the purpose of promoting health, safety, morals, or the general welfare, a county may adopt zoning and development regulation ordinances. These ordinances may be adopted as part of a unified development ordinance or as a separate ordinance. A zoning ordinance may regulate and restrict the height, number of stories and size of buildings and other structures, the percentage of lots that may be occupied, the size of yards, courts and other open spaces, the density of population, and the location and use of buildings, structures, and land for trade, industry, residence, or other purposes. The ordinance may provide density credits or severable development rights for dedicated rights-of-way pursuant to G.S. 136-66.10 or G.S. 136-66.11.

(b)       (1)        These regulations may affect property used for bona fide farm purposes only as provided in subdivision (3) of this subsection. This subsection does not limit regulation under this Part with respect to the use of farm property for nonfarm purposes.

(2)        Except as provided in G.S. 106-743.4 for farms that are subject to a conservation agreement under G.S. 106-743.2, bona fide farm purposes include the production and activities relating or incidental to the production of crops, grains, fruits, vegetables, ornamental and flowering plants, dairy, livestock, poultry, and all other forms of agriculture, as defined in G.S. 106-581.1. For purposes of this subdivision, "when performed on the farm" in G.S. 106-581.1(6) shall include the farm within the jurisdiction of the county and any other farm owned or leased to or from others by the bona fide farm operator, no matter where located. For purposes of this subdivision, the production of a nonfarm product that the Department of Agriculture and Consumer Services recognizes as a "Goodness Grows in North Carolina" product that is produced on a farm subject to a conservation agreement under G.S. 106-743.2 is a bona fide farm purpose. For purposes of determining whether a property is being used for bona fide farm purposes, any of the following shall constitute sufficient evidence that the property is being used for bona fide farm purposes:

a.         A farm sales tax exemption certificate issued by the Department of Revenue.

b.         A copy of the property tax listing showing that the property is eligible for participation in the present use value program pursuant to G.S. 105-277.3.

c.         A copy of the farm owner's or operator's Schedule F from the owner's or operator's most recent federal income tax return.

d.         A forest management plan.

e.         A Farm Identification Number issued by the United States Department of Agriculture Farm Service Agency.

(3)        The definitions set out in G.S. 106-802 apply to this subdivision. A county may adopt zoning regulations governing swine farms served by animal waste management systems having a design capacity of 600,000 pounds steady state live weight (SSLW) or greater provided that the zoning regulations may not have the effect of excluding swine farms served by an animal waste management system having a design capacity of 600,000 pounds SSLW or greater from the entire zoning jurisdiction.

(c)        The regulations may provide that a board of adjustment may determine and vary their application in harmony with their general purpose and intent and in accordance with general or specific rules therein contained, provided no change in permitted uses may be authorized by variance.

(c1)      The regulations may also provide that the board of adjustment, the planning board, or the board of commissioners may issue special use permits or conditional use permits in the classes of cases or situations and in accordance with the principles, conditions, safeguards, and procedures specified therein and may impose reasonable and appropriate conditions and safeguards upon these permits. Conditions and safeguards imposed under this subsection shall not include requirements for which the county does not have authority under statute to regulate nor requirements for which the courts have held to be unenforceable if imposed directly by the county. Where appropriate, the conditions may include requirements that street and utility rights-of-way be dedicated to the public and that recreational space be provided. When deciding special use permits or conditional use permits, the board of county commissioners or planning board shall follow quasi-judicial procedures. Notice of hearings on special or conditional use permit applications shall be as provided in G.S. 160A-388(a2). No vote greater than a majority vote shall be required for the board of county commissioners or planning board to issue such permits. For the purposes of this section, vacant positions on the board and members who are disqualified from voting on a quasi-judicial matter shall not be considered "members of the board" for calculation of the requisite majority. Every such decision of the board of county commissioners or planning board shall be subject to review of the superior court in the nature of certiorari consistent with G.S. 160A-388.

(d)       A county may regulate the development over estuarine waters and over lands covered by navigable waters owned by the State pursuant to G.S. 146-12, within the bounds of that county.

(e)        For the purpose of this section, the term "structures" shall include floating homes.

(f)        Repealed by Session Laws 2005-426, s. 5(b), effective January 1, 2006.

(g)        A member of the board of county commissioners shall not vote on any zoning map or text amendment where the outcome of the matter being considered is reasonably likely to have a direct, substantial, and readily identifiable financial impact on the member. Members of appointed boards providing advice to the board of county commissioners shall not vote on recommendations regarding any zoning map or text amendment where the outcome of the matter being considered is reasonably likely to have a direct, substantial, and readily identifiable financial impact on the member.

(h)        As provided in this subsection, counties may adopt temporary moratoria on any county development approval required by law. county development approval required by law, except for the purpose of developing and adopting new or amended plans or ordinances as to residential uses. The duration of any moratorium shall be reasonable in light of the specific conditions that warrant imposition of the moratorium and may not exceed the period of time necessary to correct, modify, or resolve such conditions. Except in cases of imminent and substantial threat to public health or safety, before adopting an ordinance imposing a development moratorium with a duration of 60 days or any shorter period, the board of commissioners shall hold a public hearing and shall publish a notice of the hearing in a newspaper having general circulation in the area not less than seven days before the date set for the hearing. A development moratorium with a duration of 61 days or longer, and any extension of a moratorium so that the total duration is 61 days or longer, is subject to the notice and hearing requirements of G.S. 153A-323. Absent an imminent threat to public health or safety, a development moratorium adopted pursuant to this section shall not apply to any project for which a valid building permit issued pursuant to G.S. 153A-357 is outstanding, to any project for which a conditional use permit application or special use permit application has been accepted, to development set forth in a site-specific or phased development plan approved pursuant to G.S. 153A-344.1, to development for which substantial expenditures have already been made in good faith reliance on a prior valid administrative or quasi-judicial permit or approval, or to preliminary or final subdivision plats that have been accepted for review by the county prior to the call for public hearing to adopt the moratorium. Any preliminary subdivision plat accepted for review by the county prior to the call for public hearing, if subsequently approved, shall be allowed to proceed to final plat approval without being subject to the moratorium.

Any ordinance establishing a development moratorium must expressly include at the time of adoption each of the following:

(1)        A clear statement of the problems or conditions necessitating the moratorium and what courses of action, alternative to a moratorium, were considered by the county and why those alternative courses of action were not deemed adequate.

(2)        A clear statement of the development approvals subject to the moratorium and how a moratorium on those approvals will address the problems or conditions leading to imposition of the moratorium.

(3)        An express date for termination of the moratorium and a statement setting forth why that duration is reasonably necessary to address the problems or conditions leading to imposition of the moratorium.

(4)        A clear statement of the actions, and the schedule for those actions, proposed to be taken by the county during the duration of the moratorium to address the problems or conditions leading to imposition of the moratorium.

No moratorium may be subsequently renewed or extended for any additional period unless the city shall have taken all reasonable and feasible steps proposed to be taken by the county in its ordinance establishing the moratorium to address the problems or conditions leading to imposition of the moratorium and unless new facts and conditions warrant an extension. Any ordinance renewing or extending a development moratorium must expressly include, at the time of adoption, the findings set forth in subdivisions (1) through (4) of this subsection, including what new facts or conditions warrant the extension.

Any person aggrieved by the imposition of a moratorium on development approvals required by law may apply to the appropriate division of the General Court of Justice for an order enjoining the enforcement of the moratorium, and the court shall have jurisdiction to issue that order. Actions brought pursuant to this section shall be set down for immediate hearing, and subsequent proceedings in those actions shall be accorded priority by the trial and appellate courts. In any such action, the county shall have the burden of showing compliance with the procedural requirements of this subsection.

(i)         In order to encourage construction that uses sustainable design principles and to improve energy efficiency in buildings, a county may charge reduced building permit fees or provide partial rebates of building permit fees for buildings that are constructed or renovated using design principles that conform to or exceed one or more of the following certifications or ratings:

(1)        Leadership in Energy and Environmental Design (LEED) certification or higher rating under certification standards adopted by the U.S. Green Building Council.

(2)        A One Globe or higher rating under the Green Globes program standards adopted by the Green Building Initiative.

(3)        A certification or rating by another nationally recognized certification or rating system that is equivalent or greater than those listed in subdivisions (1) and (2) of this subsection.

(j)         An ordinance adopted pursuant to this section shall not prohibit single-family detached residential uses constructed in accordance with the North Carolina State Building Code on lots greater than 10 acres in size in zoning districts where more than fifty percent (50%) of the land is in use for agricultural or silvicultural purposes, except that this restriction shall not apply to commercial or industrial districts where a broad variety of commercial or industrial uses are permissible. An ordinance adopted pursuant to this section shall not require that a lot greater than 10 acres in size have frontage on a public road or county-approved private road, or be served by public water or sewer lines, in order to be developed for single-family residential purposes.

(k)        A zoning or unified development ordinance may not differentiate in terms of the regulations applicable to fraternities or sororities between those fraternities or sororities that are approved or recognized by a college or university and those that are not.

(l)         Any zoning and development regulation ordinance relating to building design elements adopted under this Part, under Part 2 of this Article, or under any recommendation made under G.S. 160A-452(6)c. may not be applied to any structures subject to regulation under the North Carolina Residential Code for One- and Two-Family Dwellings except under one or more of the following circumstances:

(1)        The structures are located in an area designated as a local historic district pursuant to Part 3C of Article 19 of Chapter 160A of the General Statutes.

(2)        The structures are located in an area designated as a historic district on the National Register of Historic Places.

(3)        The structures are individually designated as local, State, or national historic landmarks.

(4)        The regulations are directly and substantially related to the requirements of applicable safety codes adopted under G.S. 143-138.

(5)        Where the regulations are applied to manufactured housing in a manner consistent with G.S. 153A-341.1 and federal law.

(6)        Where the regulations are adopted as a condition of participation in the National Flood Insurance Program.

Regulations prohibited by this subsection may not be applied, directly or indirectly, in any zoning district, special use district, conditional use district, or conditional district unless voluntarily consented to by the owners of all the property to which those regulations may be applied as part of and in the course of the process of seeking and obtaining a zoning amendment or a zoning, subdivision, or development approval, nor may any such regulations be applied indirectly as part of a review pursuant to G.S. 153A-341 of any proposed zoning amendment for consistency with an adopted comprehensive plan or other applicable officially adopted plan. For the purposes of this subsection, the phrase "building design elements" means exterior building color; type or style of exterior cladding material; style or materials of roof structures or porches; exterior nonstructural architectural ornamentation; location or architectural styling of windows and doors, including garage doors; the number and types of rooms; and the interior layout of rooms. The phrase "building design elements" does not include any of the following: (i) the height, bulk, orientation, or location of a structure on a zoning lot; (ii) the use of buffering or screening to minimize visual impacts, to mitigate the impacts of light and noise, or to protect the privacy of neighbors; or (iii) regulations adopted pursuant to this Article governing the permitted uses of land or structures subject to the North Carolina Residential Code for One- and Two-Family Dwellings.

(m)       Nothing in subsection (l) of this section shall affect the validity or enforceability of private covenants or other contractual agreements among property owners relating to building design elements.

(n)        Fence wraps displaying signage when affixed to perimeter fencing at a construction site are exempt from zoning regulation pertaining to signage under this Article until the certificate of occupancy is issued for the final portion of any construction at that site or 24 months from the time the fence wrap was installed, whichever is shorter. If construction is not completed at the end of 24 months from the time the fence wrap was installed, the county may regulate the signage but shall continue to allow fence wrapping materials to be affixed to the perimeter fencing. No fence wrap affixed pursuant to this subsection may display any advertising other than advertising sponsored by a person directly involved in the construction project and for which monetary compensation for the advertisement is not paid or required.  (1959, c. 1006, s. 1; 1967, c. 1208, s. 4; 1973, c. 822, s. 1; 1981, c. 891, s. 6; 1983, c. 441; 1985, c. 442, s. 2; 1987, c. 747, s. 12; 1991, c. 69, s. 1; 1997-458, s. 2.1; 2005-390, s. 6; 2005-426, s. 5(b); 2006-259, s. 26(a); 2007-381, s. 1; 2011-286, s. 1; 2011-363, s. 1; 2011-384, s. 5; 2013-126, ss. 5, 8; 2013-347, s. 1; 2013-413, s. 6(a); 2015-86, s. 2; 2015-246, ss. 3.1(b), 4(a); 2015-286, s. 1.8(b).)

 

§ 153A-341.  Purposes in view.

Zoning regulations shall be made in accordance with a comprehensive plan. Prior to adopting or rejecting any zoning amendment, the governing board shall adopt a statement describing whether its action is consistent with an adopted comprehensive plan and explaining why the board considers the action taken to be reasonable and in the public interest. That statement is not subject to judicial review.

The planning board shall advise and comment on whether the proposed amendment is consistent with any comprehensive plan that has been adopted and any other officially adopted plan that is applicable. The planning board shall provide a written recommendation to the board of county commissioners that addresses plan consistency and other matters as deemed appropriate by the planning board, but a comment by the planning board that a proposed amendment is inconsistent with the comprehensive plan shall not preclude consideration or approval of the proposed amendment by the governing board.

Zoning regulations shall be designed to promote the public health, safety, and general welfare. To that end, the regulations may address, among other things, the following public purposes: to provide adequate light and air; to prevent the overcrowding of land; to avoid undue concentration of population; to lessen congestion in the streets; to secure safety from fire, panic, and dangers; and to facilitate the efficient and adequate provision of transportation, water, sewerage, schools, parks, and other public requirements. The regulations shall be made with reasonable consideration as to, among other things, the character of the district and its peculiar suitability for particular uses, and with a view to conserving the value of buildings and encouraging the most appropriate use of land throughout the county. In addition, the regulations shall be made with reasonable consideration to expansion and development of any cities within the county, so as to provide for their orderly growth and development. (1959, c. 1006, s. 1; 1973, c. 822, s. 1; 2005-426, s. 7(b).)

 

§ 153A-341.1.  Zoning regulations for manufactured homes.

The provisions of G.S. 160A-383.1 shall apply to counties. (1987, c. 805, s. 2.)

 

§ 153A-341.2.  Reasonable accommodation of amateur radio antennas.

A county ordinance based on health, safety, or aesthetic considerations that regulates the placement, screening, or height of the antennas or support structures of amateur radio operators must reasonably accommodate amateur radio communications and must represent the minimum practicable regulation necessary to accomplish the purpose of the county. A county may not restrict antennas or antenna support structures of amateur radio operators to heights of 90 feet or lower unless the restriction is necessary to achieve a clearly defined health, safety, or aesthetic objective of the county. (2007-147, s. 2.)

 

§ 153A-341.3.  Zoning of temporary health care structures.

A county exercising powers under this Article shall comply with G.S. 160A-383.5.  (2014-94, s. 1.)

 

§ 153A-342.  Districts; zoning less than entire jurisdiction.

(a)        A county may divide its territorial jurisdiction into districts of any number, shape, and area that it may consider best suited to carry out the purposes of this Part. Within these districts a county may regulate and restrict the erection, construction, reconstruction, alteration, repair, or use of buildings, structures, or land. Such districts may include, but shall not be limited to, general use districts, in which a variety of uses are permissible in accordance with general standards; overlay districts, in which additional requirements are imposed on certain properties within one or more underlying general or special use districts; special use districts or conditional use districts, in which uses are permitted only upon the issuance of a special use permit or a conditional use permit and conditional zoning districts, in which site plans and individualized development conditions are imposed.

(b)        Property may be placed in a special use district, conditional use district, or conditional district only in response to a petition by the owners of all the property to be included. Specific conditions applicable to the districts may be proposed by the petitioner or the county or its agencies, but only those conditions mutually approved by the county and the petitioner may be incorporated into the zoning regulations or permit requirements. Conditions and site-specific standards imposed in a conditional district shall be limited to those that address the conformance of the development and use of the site to county ordinances and an officially adopted comprehensive or other plan and those that address the impacts reasonably expected to be generated by the development or use of the site.

A statement analyzing the reasonableness of the proposed rezoning shall be prepared for each petition for a rezoning to a special or conditional use district, or a conditional district, or other small-scale rezoning.

(c)        Except as authorized by the foregoing, all regulations shall be uniform for each class or kind of building throughout each district, but the regulations in one district may differ from those in other districts.

(d)       A county may determine that the public interest does not require that the entire territorial jurisdiction of the county be zoned and may designate one or more portions of that jurisdiction as a zoning area or areas. A zoning area must originally contain at least 640 acres and at least 10 separate tracts of land in separate ownership and may thereafter be expanded by the addition of any amount of territory. A zoning area may be regulated in the same manner as if the entire county were zoned, and the remainder of the county need not be regulated. (1959, c. 1006, s. 1; 1965, c. 194, s. 2; 1973, c. 822, s. 1; 1985, c. 607, s. 3; 2005-426, s. 6(b).)

 

§ 153A-343.  Method of procedure.

(a)        The board of commissioners shall, in accordance with the provisions of this Article, provide for the manner in which zoning regulations and restrictions and the boundaries of zoning districts shall be determined, established, and enforced, and from time to time amended, supplemented, or changed. The procedures adopted pursuant to this section shall provide that whenever there is a zoning map amendment, the owner of that parcel of land as shown on the county tax listing, and the owners of all parcels of land abutting that parcel of land as shown on the county tax listing, shall be mailed a notice of a public hearing on the proposed amendment by first class mail at the last addresses listed for such owners on the county tax abstracts. This notice must be deposited in the mail at least 10 but not more than 25 days prior to the date of the public hearing. Except for a county-initiated zoning map amendment, when an application is filed to request a zoning map amendment and that application is not made by the owner of the parcel of land to which the amendment would apply, the applicant shall certify to the board of commissioners that the owner of the parcel of land as shown on the county tax listing has received actual notice of the proposed amendment and a copy of the notice of public hearing. The person or persons required to provide notice shall certify to the board of commissioners that proper notice has been provided in fact, and such certificate shall be deemed conclusive in the absence of fraud.

(b)        The first class mail notice required under subsection (a) of this section shall not be required if the zoning map amendment directly affects more than 50 properties, owned by a total of at least 50 different property owners, and the county elects to use the expanded published notice provided for in this subsection. In this instance, a county may elect to either make the mailed notice provided for in subsection (a) of this section or may as an alternative elect to publish notice of the hearings required by G.S. 153A-323, but provided that each of the advertisements shall not be less than one-half of a newspaper page in size. The advertisement shall only be effective for property owners who reside in the area of general circulation of the newspaper which publishes the notice. Property owners who reside outside of the newspaper circulation area, according to the address listed on the most recent property tax listing for the affected property, shall be notified according to the provisions of subsection (a) of this section.

(b1)      Actual notice of the proposed amendment and a copy of the notice of public hearing required under subsection (a) of this section shall be by any manner permitted under G.S. 1A-1, Rule 4(j). If notice cannot with due diligence be achieved by personal delivery, registered or certified mail, or by a designated delivery service authorized pursuant to 26 U.S.C. § 7502(f)(2), notice may be given by publication consistent with G.S. 1A-1, Rule 4(j1). This subsection applies only to an application to request a zoning map amendment where the application is not made by the owner of the parcel of land to which the amendment would apply. This subsection does not apply to a county-initiated zoning map amendment.

(c)        Repealed by Session Laws 2005-418, s. 4, effective January 1, 2006.

(d)       When a zoning map amendment is proposed, the county shall prominently post a notice of the public hearing on the site proposed for rezoning or on an adjacent public street or highway right-of-way. When multiple parcels are included within a proposed zoning map amendment, a posting on each individual parcel is not required, but the county shall post sufficient notices to provide reasonable notice to interested persons.  (1973, c. 822, s. 1; 1985, c. 595, s. 1; 1987, c. 807, s. 2; 1989 (Reg. Sess., 1990), c. 980, s. 2; 1993, c. 469, s. 2; 1995, c. 261, s. 1; c. 546, s. 2; 1997-456, s. 25; 2005-418, s. 4(b); 2009-178, s. 1.)

 

§ 153A-344.  Planning board; zoning plan; certification to board of commissioners.

(a)        To initially exercise the powers conferred by this Part, a county shall create or designate a planning board under the provisions of this Article or of a local act. The planning board shall prepare or shall review and comment upon a proposed zoning ordinance, including both the full text of such ordinance and maps showing proposed district boundaries. The planning board may hold public hearings in the course of preparing the ordinance. Upon completion, the planning board shall make a written recommendation regarding adoption of the ordinance to the board of commissioners. The board of commissioners shall not hold the public hearing required by G.S. 153A-323 or take action until it has received a recommendation regarding the ordinance from the planning board. Following its required public hearing, the board of commissioners may refer the ordinance back to the planning board for any further recommendations that the board may wish to make prior to final action by the board in adopting, modifying and adopting, or rejecting the ordinance.

Subsequent to initial adoption of a zoning ordinance, all proposed amendments to the zoning ordinance or zoning map shall be submitted to the planning board for review and comment. If no written report is received from the planning board within 30 days of referral of the amendment to that board, the board of county commissioners may proceed in its consideration of the amendment without the planning board report. The board of commissioners is not bound by the recommendations, if any, of the planning board.

(b)        Amendments in zoning ordinances shall not be applicable or enforceable without consent of the owner with regard to buildings and uses for which either (i) building permits have been issued pursuant to G.S. 153A-357 prior to the enactment of the ordinance making the change or changes so long as the permits remain valid and unexpired pursuant to G.S. 153A-358 and unrevoked pursuant to G.S. 153A-362 or (ii) a vested right has been established pursuant to G.S. 153A-344.1 and such vested right remains valid and unexpired pursuant to G.S. 153A-344.1.

(b1)      Amendments in zoning ordinances, subdivision ordinances, and unified development ordinances shall not be applicable or enforceable without the written consent of the owner with regard to a multi-phased development as defined in G.S. 153A-344.1(b)(7). A multi-phased development shall be vested for the entire development with the zoning ordinances, subdivision ordinances, and unified development ordinances then in place at the time a site plan approval is granted for the initial phase of the multi-phased development. A right which has been vested as provided for in this subsection shall remain vested for a period of seven years from the time a site plan approval is granted for the initial phase of the multi-phased development.  (1959, c. 1006, s. 1; 1965, c. 194, s. 3; 1973, c. 822, s. 1; 1979, c. 611, s. 3; 1985, c. 540, s. 1; 1989 (Reg. Sess., 1990), c. 996, s. 5; 2005-418, s. 7(b); 2016-111, s. 3.)

 

§ 153A-344.1.  Vesting rights.

(a)        The General Assembly finds and declares that it is necessary and desirable, as a matter of public policy, to provide for the establishment of certain vested rights in order to ensure reasonable certainty, stability, and fairness in the land-use planning process, secure the reasonable expectations of landowners, and foster cooperation between the public and private sectors in the area of land-use planning. Furthermore, the General Assembly recognizes that county approval of land-use development typically follows significant landowner investment in site evaluation, planning, development costs, consultant fees, and related expenses.

The ability of a landowner to obtain a vested right after county approval of a site specific development plan or a phased development plan will preserve the prerogatives and authority of local elected officials with respect to land-use matters. There will be ample opportunities for public participation and the public interest will be served. These provisions will strike an appropriate balance between private expectations and the public interest, while scrupulously protecting the public health, safety, and welfare.

(b)        Definitions.

(1)        "Landowner" means any owner of a legal or equitable interest in real property, including the heirs, devisees, successors, assigns, and personal representative of such owner. The landowner may allow a person holding a valid option to purchase to act as his agent or representative for purposes of submitting a proposed site specific development plan or a phased development plan under this section, in the manner allowed by ordinance.

(2)        "County" shall have the same meaning as set forth in G.S. 153A-1(3).

(3)        "Phased development plan" means a plan which has been submitted to a county by a landowner for phased development which shows the type and intensity of use for a specific parcel or parcels with a lesser degree of certainty than the plan determined by the county to be a site specific development plan.

(4)        "Property" means all real property subject to zoning regulations and restrictions and zone boundaries by a county.

(5)        "Site specific development plan" means a plan which has been submitted to a county by a landowner describing with reasonable certainty the type and intensity of use for a specific parcel or parcels of property. Such plan may be in the form of, but not be limited to, any of the following plans or approvals: A planned unit development plan, a subdivision plat, a preliminary or general development plan, a conditional or special use permit, a conditional or special use district zoning plan, or any other land-use approval designation as may be utilized by a county. Unless otherwise expressly provided by the county such a plan shall include the approximate boundaries of the site; significant topographical and other natural features effecting development of the site; the approximate location on the site of the proposed buildings, structures, and other improvements; the approximate dimensions, including height, of the proposed buildings and other structures; and the approximate location of all existing and proposed infrastructure on the site, including water, sewer, roads, and pedestrian walkways. What constitutes a site specific development plan under this section that would trigger a vested right shall be finally determined by the county pursuant to an ordinance, and the document that triggers such vesting shall be so identified at the time of its approval. However, at a minimum, the ordinance to be adopted by the county shall designate a vesting point earlier than the issuance of a building permit. A variance shall not constitute a site specific development plan, and approval of a site specific development plan with the condition that a variance be obtained shall not confer a vested right unless and until the necessary variance is obtained. Neither a sketch plan nor any other document which fails to describe with reasonable certainty the type and intensity of use for a specified parcel or parcels or property may constitute a site specific development plan.

(6)        "Vested right" means the right to undertake and complete the development and use of property under the terms and conditions of an approved site specific development plan or an approved phased development plan.

(7)        "Multi-phased development" means a development containing 100 acres or more that (i) is submitted for site plan approval for construction to occur in more than one phase and (ii) is subject to a master development plan with committed elements, including a requirement to offer land for public use as a condition of its master development plan approval.

(c)        Establishment of vested right.

A vested right shall be deemed established with respect to any property upon the valid approval, or conditional approval, of a site specific development plan or a phased development plan, following notice and public hearing by the county with jurisdiction over the property. Such vested right shall confer upon the landowner the right to undertake and complete the development and use of said property under the terms and conditions of the site specific development plan or the phased development plan including any amendments thereto. A county may approve a site specific development plan or a phased development plan upon such terms and conditions as may reasonably be necessary to protect the public health, safety, and welfare. Such conditional approval shall result in a vested right, although failure to abide by such terms and conditions will result in a forfeiture of vested rights. A county shall not require a landowner to waive his vested rights as a condition of developmental approval. A site specific development plan or a phased development plan shall be deemed approved upon the effective date of the county's action or ordinance relating thereto.

(d)       Duration and termination of vested right.

(1)        A right which has been vested as provided for in this section shall remain vested for a period of two years. This vesting shall not be extended by any amendments or modifications to a site specific development plan unless expressly provided by the county.

(2)        Notwithstanding the provisions of subsection (d)(1), a county may provide that rights shall be vested for a period exceeding two years but not exceeding five years where warranted in light of all relevant circumstances, including, but not limited to, the size and phasing of development, the level of investment, the need for the development, economic cycles, and market conditions. These determinations shall be in the sound discretion of the county.

(3)        Notwithstanding the provisions of (d)(1) and (d)(2), the county may provide by ordinance that approval by a county of a phased development plan shall vest the zoning classification or classifications so approved for a period not to exceed five years. The document that triggers such vesting shall be so identified at the time of its approval. The county still may require the landowner to submit a site specific development plan for approval by the county with respect to each phase or phases in order to obtain final approval to develop within the restrictions of the vested zoning classification or classifications. Nothing in this section shall be construed to require a county to adopt an ordinance providing for vesting of rights upon approval of a phased development plan.

(4)        Following approval or conditional approval of a site specific development plan or a phased development plan, nothing in this section shall exempt such a plan from subsequent reviews and approvals by the county to ensure compliance with the terms and conditions of the original approval, provided that such reviews and approvals are not inconsistent with said original approval. Nothing in this section shall prohibit the county from revoking the original approval for failure to comply with applicable terms and conditions of the approval or the zoning ordinance.

(5)        Upon issuance of a building permit, the provisions of G.S. 153A-358 and G.S. 153A-362 shall apply, except that a permit shall not expire or be revoked because of the running of time while a vested right under this section is outstanding.

(6)        A right which has been vested as provided in this section shall terminate at the end of the applicable vesting period with respect to buildings and uses for which no valid building permit applications have been filed.

(e)        Subsequent changes prohibited; exceptions.

(1)        A vested right, once established as provided for in this section, precludes any zoning action by a county which would change, alter, impair, prevent, diminish, or otherwise delay the development or use of the property as set forth in an approved site specific development plan or an approved phased development plan, except:

a.         With the written consent of the affected landowner;

b.         Upon findings, by ordinance after notice and a public hearing, that natural or man-made hazards on or in the immediate vicinity of the property, if uncorrected, would pose a serious threat to the public health, safety, and welfare if the project were to proceed as contemplated in the site specific development plan or the phased development plan;

c.         To the extent that the affected landowner receives compensation for all costs, expenses, and other losses incurred by the landowner, including, but not limited to, all fees paid in consideration of financing, and all architectural, planning, marketing, legal, and other consultant's fees incurred after approval by the county, together with interest thereon at the legal rate until paid. Compensation shall not include any diminution in the value of the property which is caused by such action;

d.         Upon findings, by ordinance after notice and a hearing, that the landowner or his representative intentionally supplied inaccurate information or made material misrepresentations which made a difference in the approval by the county of the site specific development plan or the phased development plan; or

e.         Upon the enactment or promulgation of a State or federal law or regulation which precludes development as contemplated in the site specific development plan or the phased development plan, in which case the county may modify the affected provisions, upon a finding that the change in State or federal law has a fundamental effect on the plan, by ordinance after notice and a hearing.

(2)        The establishment of a vested right shall not preclude the application of overlay zoning which imposes additional requirements but does not affect the allowable type or intensity of use, or ordinances or regulations which are general in nature and are applicable to all property subject to land-use regulation by a county, including, but not limited to, building, fire, plumbing, electrical, and mechanical codes. Otherwise applicable new regulations shall become effective with respect to property which is subject to a site specific development plan or a phased development plan upon the expiration or termination of the vesting rights period provided for in this section.

(3)        Notwithstanding any provision of this section, the establishment of a vested right shall not preclude, change or impair the authority of a county to adopt and enforce zoning ordinance provisions governing nonconforming situations or uses.

(f)        Miscellaneous provisions.

(1)        A vested right obtained under this section is not a personal right, but shall attach to and run with the applicable property. After approval of a site specific development plan or a phased development plan, all successors to the original landowner shall be entitled to exercise such rights.

(2)        Nothing in this section shall preclude judicial determination, based on common-law principles or other statutory provisions, that a vested right exists in a particular case or that a compensable taking has occurred. Except as expressly provided in this section, nothing in this section shall be construed to alter the existing common law.

(3)        In the event a county fails to adopt an ordinance setting forth what constitutes a site specific development plan triggering a vested right, a landowner may establish a vested right with respect to property upon the approval of a zoning permit, or otherwise may seek appropriate relief from the Superior Court Division of the General Court of Justice.  (1989 (Reg. Sess., 1990), c. 996, s. 6; 2016-111, s. 4.)

 

§ 153A-345: Repealed by Session Laws 2013-126, s. 3(a), effective October 1, 2013, and applicable to actions taken on or after that date by any board of adjustment.

 

§ 153A-345.1.  Board of adjustment.

(a)        The provisions of G.S. 160A-388 are applicable to counties.

(b)        For the purposes of this section, as used in G.S. 160A-388, the term "city council" is deemed to refer to the board of county commissioners, and the terms "city" or "municipality" are deemed to refer to the county.

(c)        If a board of county commissioners does not zone the entire territorial jurisdiction of the county, each designated zoning area shall, if practicable, have at least one resident as a member of the board of adjustment; otherwise, the provisions of G.S. 153A-25 regarding qualifications for appointive office shall apply to board of adjustment appointments.  (2013-126, s. 3(b).)

 

§ 153A-346.  Conflict with other laws.

(a)        When regulations made under authority of this Part require a greater width or size of yards or courts, or require a lower height of a building or fewer number of stories, or require a greater percentage of a lot to be left unoccupied, or impose other higher standards than are required in any other statute or local ordinance or regulation, the regulations made under authority of this Part govern. When the provisions of any other statute or local ordinance or regulation require a greater width or size of yards or courts, or require a lower height of a building or a fewer number of stories, or require a greater percentage of a lot to be left unoccupied, or impose other higher standards than are required by regulations made under authority of this Part, the provisions of the other statute or local ordinance or regulation govern.

(b)        When adopting regulations under this Part, a county may not use a definition of dwelling unit, bedroom, or sleeping unit that is more expansive than any definition of the same in another statute or in a rule adopted by a State agency.  (1959, c. 1006, s. 1; 1973, c. 822, s. 1; 2015-246, s. 18(a).)

 

§ 153A-347.  Part applicable to buildings constructed by the State and its subdivisions; exception.

Each provision of this Part is applicable to the erection, construction, and use of buildings by the State of North Carolina and its political subdivisions.

Notwithstanding the provisions of any general or local law or ordinance, no land owned by the State of North Carolina may be included within an overlay district or a special use or conditional use district without approval of the Council of State. (1959, c. 1006, s. 1; 1973, c. 822, s. 1; 1985, c. 607, s. 4.)

 

§ 153A-348.  Statute of limitations.

(a)        A cause of action as to the validity of any ordinance adopting or amending a zoning map or approving a special use, conditional use, or conditional zoning district rezoning request adopted under this Part or other applicable law shall accrue upon adoption of  such ordinance and shall be brought within two months as provided in G.S. 1-54.1.

(b)        Except as otherwise provided in subsection (a) of this section, an action challenging the validity of any zoning or unified development ordinance or any provision thereof adopted under this Part or other applicable law shall be brought within one year of the accrual of such action. Such an action accrues when the party bringing such action first has standing to challenge the ordinance. A challenge to an ordinance on the basis of an alleged defect in the adoption process shall be brought within three years after the adoption of the ordinance.

(c)        Nothing in this section or in G.S. 1-54(10) or G.S. 1-54.1 shall bar a party in an action involving the enforcement of a zoning or unified development ordinance from raising as a defense to such enforcement action the invalidity of the ordinance. Nothing in this section or in G.S. 1-54(10) or G.S. 1-54.1 shall bar a party who files a timely appeal from an order, requirement, decision, or determination made by an administrative official contending that such party is in violation of a zoning or unified development ordinance from raising in the appeal the invalidity of such ordinance as a defense to such order, requirement, decision, or determination. A party in an enforcement action or appeal may not assert the invalidity of the ordinance on the basis of an alleged defect in the adoption process unless the defense is formally raised within three years of the adoption of the challenged ordinance.

(d)       When a use constituting a violation of a zoning or unified development ordinance is in existence prior to adoption of the zoning or unified development ordinance creating the violation, and that use is grandfathered and subsequently terminated for any reason, a county shall bring an enforcement action within 10 years of the date of the termination of the grandfathered status, unless the violation poses an imminent hazard to health or public safety.  (1981, c. 705, s. 2; 1995 (Reg. Sess., 1996), c. 746, s. 6; 2011-326, s. 22(a); 2011-384, s. 3; 2013-413, s. 5(a).)

 

§ 153A-349.  Appeals in the nature of certiorari.

(a)        Whenever appeals of quasi-judicial decisions of decision-making boards are to superior court and in the nature of certiorari as required by this Article, the provisions of G.S. 160A-393 shall be applicable to those appeals.

(b)        For purposes of this section, as used in G.S. 160A-393, the term "city council" shall be deemed to refer to the "board of commissioners," and the term "city" or "municipal" shall be deemed to refer to the "county."

(c)        Repealed by Session Laws 2013-126, s. 9, effective October 1, 2013, and applicable to actions taken on or after that date by any board of adjustment.  (2009-421, s. 1(b); 2013-126, s. 9.)

 

Part 3A. Development Agreements.

§ 153A-349.1.  Authorization for development agreements.

(a)        The General Assembly finds:

(1)        Large-scale development projects often occur in multiple phases extending over a period of years, requiring a long-term commitment of both public and private resources.

(2)        Such large-scale developments often create potential community impacts and potential opportunities that are difficult or impossible to accommodate within traditional zoning processes.

(3)        Because of their scale and duration, such large-scale projects often require careful integration between public capital facilities planning, financing, and construction schedules and the phasing of the private development.

(4)        Because of their scale and duration, such large-scale projects involve substantial commitments of private capital by developers, which developers are usually unwilling to risk without sufficient assurances that development standards will remain stable through the extended period of the development.

(5)        Because of their size and duration, such developments often permit communities and developers to experiment with different or nontraditional types of development concepts and standards, while still managing impacts on the surrounding areas.

(6)        To better structure and manage development approvals for such large-scale developments and ensure their proper integration into local capital facilities programs, local governments need the flexibility in negotiating such developments.

(b)        Local governments and agencies may enter into development agreements with developers, subject to the procedures and requirements of this Part. In entering into such agreements, a local government may not exercise any authority or make any commitment not authorized by general or local act and may not impose any tax or fee not authorized by otherwise applicable law.

(c)        This Part is supplemental to the powers conferred upon local governments and does not preclude or supersede rights and obligations established pursuant to other law regarding building permits, site-specific development plans, phased development plans, or other provisions of law. (2005-426, s. 9(b).)

 

§ 153A-349.2.  Definitions.

The following definitions apply in this Part:

(1)        Comprehensive plan. - The comprehensive plan, land-use plan, small area plans, neighborhood plans, transportation plan, capital improvement plan, official map, and any other plans regarding land use and development that have been officially adopted by the governing board.

(2)        Developer. - A person, including a governmental agency or redevelopment authority, who intends to undertake any development and who has a legal or equitable interest in the property to be developed.

(3)        Development. - The planning for or carrying out of a building activity, the making of a material change in the use or appearance of any structure or property, or the dividing of land into two or more parcels. "Development", as designated in a law or development permit, includes the planning for and all other activity customarily associated with it unless otherwise specified. When appropriate to the context, "development" refers to the planning for or the act of developing or to the result of development. Reference to a specific operation is not intended to mean that the operation or activity, when part of other operations or activities, is not development. Reference to particular operations is not intended to limit the generality of this item.

(4)        Development permit. - A building permit, zoning permit, subdivision approval, special or conditional use permit, variance, or any other official action of local government having the effect of permitting the development of property.

(5)        Governing body. - The board of county commissioners of a county.

(6)        Land development regulations. - Ordinances and regulations enacted by the appropriate governing body for the regulation of any aspect of development and includes zoning, subdivision, or any other land development ordinances.

(7)        Laws. - All ordinances, resolutions, regulations, comprehensive plans, land development regulations, policies, and rules adopted by a local government affecting the development of property, and includes laws governing permitted uses of the property, density, design, and improvements.

(8)        Local government. - Any county that exercises regulatory authority over and grants development permits for land development or which provides public facilities.

(9)        Local planning board. - Any planning board established pursuant to G.S. 153A-321.

(10)      Person. - An individual, corporation, business or land trust, estate, trust, partnership, association, two or more persons having a joint or common interest, State agency, or any legal entity.

(11)      Property. - All real property subject to land-use regulation by a local government and includes any improvements or structures customarily regarded as a part of real property.

(12)      Public facilities. - Major capital improvements, including, but not limited to, transportation, sanitary sewer, solid waste, drainage, potable water, educational, parks and recreational, and health systems and facilities. (2005-426, s. 9(b).)

 

§ 153A-349.3.  Local governments authorized to enter into development agreements; approval of governing body required.

(a)        A local government may establish procedures and requirements, as provided in this Part, to consider and enter into development agreements with developers. A development agreement must be approved by the governing body of a local government by ordinance.

(b)        The development agreement may, by ordinance, be incorporated, in whole or in part, into any planning, zoning, or subdivision ordinance adopted by the local government.  (2005-426, s. 9(b); 2015-246, s. 19(c).)

 

§ 153A-349.4.  Developed property criteria; permissible durations of agreements.

(a)        A local government may enter into a development agreement with a developer for the development of property as provided in this Part for developable property of any size, including property that is subject to an executed brownfields agreement pursuant to Part 5 of Article 9 of Chapter 130A of the General Statutes. Development agreements shall be of a reasonable term specified in the agreement.

(b)        Repealed by Session Laws 2015-246, s. 19(a), effective October 1, 2015.  (2005-426, s. 9(b); 2013-413, s. 44(a); 2015-246, s. 19(a).)

 

§ 153A-349.5.  Public hearing.

Before entering into a development agreement, a local government shall conduct a public hearing on the proposed agreement following the procedures set forth in G.S. 153A-323 regarding zoning ordinance adoption or amendment. The notice for the public hearing must specify the location of the property subject to the development agreement, the development uses proposed on the property, and must specify a place where a copy of the proposed development agreement can be obtained. In the event that the development agreement provides that the local government shall provide certain public facilities, the development agreement shall provide that the delivery date of such public facilities will be tied to successful performance by the developer in implementing the proposed development (such as meeting defined completion percentages or other performance standards). (2005-426, s. 9(b).)

 

§ 153A-349.6.  What development agreement must provide; what it may provide; major modification requires public notice and hearing.

(a)        A development agreement shall at a minimum include all of the following:

(1)        A legal description of the property subject to the agreement and the names of its legal and equitable property owners.

(2)        The duration of the agreement. However, the parties are not precluded from entering into subsequent development agreements that may extend the original duration period.

(3)        The development uses permitted on the property, including population densities and building types, intensities, placement on the site, and design.

(4)        A description of public facilities that will service the development, including who provides the facilities, the date any new public facilities, if needed, will be constructed, and a schedule to assure public facilities are available concurrent with the impacts of the development.

(5)        A description, where appropriate, of any reservation or dedication of land for public purposes and any provisions to protect environmentally sensitive property.

(6)        A description of all local development permits approved or needed to be approved for the development of the property together with a statement indicating that the failure of the agreement to address a particular permit, condition, term, or restriction does not relieve the developer of the necessity of complying with the law governing their permitting requirements, conditions, terms, or restrictions.

(7)        A description of any conditions, terms, restrictions, or other requirements determined to be necessary by the local government for the public health, safety, or welfare of its citizens.

(8)        A description, where appropriate, of any provisions for the preservation and restoration of historic structures.

(b)        A development agreement may provide that the entire development or any phase of it be commenced or completed within a specified period of time. The development agreement must provide a development schedule, including commencement dates and interim completion dates at no greater than five-year intervals; provided, however, the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of the development agreement pursuant to G.S. 153A-349.8 but must be judged based upon the totality of the circumstances. The development agreement may include other defined performance standards to be met by the developer. The developer may request a modification in the dates as set forth in the agreement. Consideration of a proposed major modification of the agreement shall follow the same procedures as required for initial approval of a development agreement.

(c)        If more than one local government is made party to an agreement, the agreement must specify which local government is responsible for the overall administration of the development agreement.

(d)       The development agreement also may cover any other matter not inconsistent with this Part.

(e)        Any performance guarantees under the development agreement shall comply with G.S. 160A-372(g).  (2005-426, s. 9(b); 2015-187, s. 1(d).)

 

§ 153A-349.7.  Law in effect at time of agreement governs development; exceptions.

(a)        Unless the development agreement specifically provides for the application of subsequently enacted laws, the laws applicable to development of the property subject to a development agreement are those in force at the time of execution of the agreement.

(b)        Except for grounds specified in G.S. 153A-344.1(e), a local government may not apply subsequently adopted ordinances or development policies to a development that is subject to a development agreement.

(c)        In the event State or federal law is changed after a development agreement has been entered into and the change prevents or precludes compliance with one or more provisions of the development agreement, the local government may modify the affected provisions, upon a finding that the change in State or federal law has a fundamental effect on the development agreement, by ordinance after notice and a hearing.

(d)       This section does not abrogate any rights preserved by G.S. 153A-344 or G.S. 153A-344.1, or that may vest pursuant to common law or otherwise in the absence of a development agreement. (2005-426, s. 9(b).)

 

§ 153A-349.8.  Periodic review to assess compliance with agreement; material breach by developer; notice of breach; cure of breach or modification or termination of agreement.

(a)        Procedures established pursuant to G.S. 153A-349.3 must include a provision for requiring periodic review by the zoning administrator or other appropriate officer of the local government at least every 12 months, at which time the developer must be required to demonstrate good faith compliance with the terms of the development agreement.

(b)        If, as a result of a periodic review, the local government finds and determines that the developer has committed a material breach of the terms or conditions of the agreement, the local government shall serve notice in writing, within a reasonable time after the periodic review, upon the developer setting forth with reasonable particularity the nature of the breach and the evidence supporting the finding and determination, and providing the developer a reasonable time in which to cure the material breach.

(c)        If the developer fails to cure the material breach within the time given, then the local government unilaterally may terminate or modify the development agreement; provided, the notice of termination or modification may be appealed to the board of adjustment in the manner provided by G.S. 160A-388(b1).  (2005-426, s. 9(b); 2013-126, s. 10.)

 

§ 153A-349.9.  Amendment or cancellation of development agreement by mutual consent of parties or successors in interest.

A development agreement may be amended or canceled by mutual consent of the parties to the agreement or by their successors in interest. (2005-426, s. 9(b).)

 

§ 153A-349.10.  Validity and duration of agreement entered into prior to change of jurisdiction; subsequent modification or suspension.

(a)        Except as otherwise provided by this Part, any development agreement entered into by a local government before the effective date of a change of jurisdiction shall be valid for the duration of the agreement, or eight years from the effective date of the change in jurisdiction, whichever is earlier. The parties to the development agreement and the local government assuming jurisdiction have the same rights and obligations with respect to each other regarding matters addressed in the development agreement as if the property had remained in the previous jurisdiction.

(b)        A local government assuming jurisdiction may modify or suspend the provisions of the development agreement if the local government determines that the failure of the local government to do so would place the residents of the territory subject to the development agreement, or the residents of the local government, or both, in a condition dangerous to their health or safety, or both. (2005-426, s. 9(b).)

 

§ 153A-349.11.  Developer to record agreement within 14 days; burdens and benefits inure to successors in interest.

Within 14 days after a local government enters into a development agreement, the developer shall record the agreement with the register of deeds in the county where the property is located. The burdens of the development agreement are binding upon, and the benefits of the agreement shall inure to, all successors in interest to the parties to the agreement. (2005-426, s. 9(b).)

 

§ 153A-349.12.  Applicability to local government of constitutional and statutory procedures for approval of debt.

In the event that any of the obligations of the local government in the development agreement constitute debt, the local government shall comply, at the time of the obligation to incur the debt and before the debt becomes enforceable against the local government, with any applicable constitutional and statutory procedures for the approval of this debt. (2005-426, s. 9(b).)

 

§ 153A-349.13.  Relationship of agreement to building or housing code.

A development agreement adopted pursuant to this Chapter shall not exempt the property owner or developer from compliance with the State Building Code or State or local housing codes that are not part of the local government's planning, zoning, or subdivision regulations. (2005-426, s. 9(b).)

 

Part 3B. Wireless Telecommunications Facilities.

§ 153A-349.50.  Purpose and compliance with federal law.

(a)        Purpose. - The purpose of this section is to ensure the safe and efficient integration of facilities necessary for the provision of advanced mobile broadband and wireless telecommunications services throughout the community and to ensure the ready availability of reliable wireless service to the public, government agencies, and first responders, with the intention of furthering the public safety and general welfare.

(a1)      The deployment of wireless infrastructure is critical to ensuring first responders can provide for the health and safety of all residents of North Carolina and that, consistent with section 6409 of the federal Middle Class Tax Relief and Job Creation Act of 2012, 47 U.S.C. § 1455(a), which creates a national wireless emergency communications network for use by first responders that in large measure will be dependent on facilities placed on existing wireless communications support structures, it is the policy of this State to facilitate the placement of wireless communications support structures in all areas of North Carolina. The following standards shall apply to a county's actions, as a regulatory body, in the regulation of the placement, construction, or modification of a wireless communications facility.

(b)        Compliance with the Federal Communications Act. - The placement, construction, or modification of wireless communications facilities shall be in conformity with the Federal Communications Act, 47 U.S.C. § 332 as amended, section 6409 of the federal Middle Class Tax Relief and Job Creation Act of 2012, 47 U.S.C. § 1455(a), and in accordance with the rules promulgated by the Federal Communications Commission.  (2007-526, s. 2; 2013-185, s. 2.)

 

§ 153A-349.51.  Definitions.

The following definitions apply in this Part:

(1)        Antenna. - Communications equipment that transmits, receives, or transmits and receives electromagnetic radio signals used in the provision of all types of wireless communications services.

(2)        Application. - A formal request submitted to the county to construct or modify a wireless support structure or a wireless facility.

(2a)      Base station. - A station at a specific site authorized to communicate with mobile stations, generally consisting of radio receivers, antennas, coaxial cables, power supplies, and other associated electronics.

(3)        Building permit. - An official administrative authorization issued by the county prior to beginning construction consistent with the provisions of G.S. 153A-357.

(4)        Collocation. - The placement or installation of wireless facilities on existing structures, including electrical transmission towers, water towers, buildings, and other structures capable of structurally supporting the attachment of wireless facilities in compliance with applicable codes.

(4a)      Eligible facilities request. - A request for modification of an existing wireless tower or base station that involves collocation of new transmission equipment or replacement of transmission equipment but does not include a substantial modification.

(5)        Equipment compound. - An area surrounding or near the base of a wireless support structure within which a wireless facility is located.

(5a)      Fall zone. - The area in which a wireless support structure may be expected to fall in the event of a structural failure, as measured by engineering standards.

(6)        Land development regulation. - Any ordinance enacted pursuant to this Part.

(7)        Search ring. - The area within which a wireless support facility or wireless facility must be located in order to meet service objectives of the wireless service provider using the wireless facility or wireless support structure.

(7a)      Substantial modification. - The mounting of a proposed wireless facility on a wireless support structure that substantially changes the physical dimensions of the support structure. A mounting is presumed to be a substantial modification if it meets any one or more of the criteria listed below. The burden is on the local government to demonstrate that a mounting that does not meet the listed criteria constitutes a substantial change to the physical dimensions of the wireless support structure.

a.         Increasing the existing vertical height of the structure by the greater of (i) more than ten percent (10%) or (ii) the height of one additional antenna array with separation from the nearest existing antenna not to exceed 20 feet.

b.         Except where necessary to shelter the antenna from inclement weather or to connect the antenna to the tower via cable, adding an appurtenance to the body of a wireless support structure that protrudes horizontally from the edge of the wireless support structure the greater of (i) more than 20 feet or (ii) more than the width of the wireless support structure at the level of the appurtenance.

c.         Increasing the square footage of the existing equipment compound by more than 2,500 square feet.

(8)        Utility pole. - A structure that is designed for and used to carry lines, cables, or wires for telephone, cable television, or electricity, or to provide lighting.

(8a)      Water tower. - A water storage tank, a standpipe, or an elevated tank situated on a support structure originally constructed for use as a reservoir or facility to store or deliver water.

(9)        Wireless facility. - The set of equipment and network components, exclusive of the underlying wireless support structure or tower, including antennas, transmitters, receivers, base stations, power supplies, cabling, and associated equipment necessary to provide wireless data and wireless telecommunications services to a discrete geographic area.

(10)      Wireless support structure. - A new or existing structure, such as a monopole, lattice tower, or guyed tower that is designed to support or capable of supporting wireless facilities. A utility pole is not a wireless support structure.  (2007-526, s. 2; 2013-185, s. 2.)

 

§ 153A-349.51A.  Local authority.

A county may plan for and regulate the siting or modification of wireless support structures and wireless facilities in accordance with land development regulations and in conformity with this Part. Except as expressly stated, nothing in this Part shall limit a county from regulating applications to construct, modify, or maintain wireless support structures, or construct, modify, maintain, or collocate wireless facilities on a wireless support structure based on consideration of land use, public safety, and zoning considerations, including aesthetics, landscaping, structural design, setbacks, and fall zones, or State and local building code requirements, consistent with the provisions of federal law provided in G.S. 153A-349.50. For purposes of this Part, public safety includes, without limitation, federal, State, and local safety regulations but does not include requirements relating to radio frequency emissions of wireless facilities.  (2013-185, s. 2.)

 

§ 153A-349.52.  Construction of new wireless support structures or substantial modifications of wireless support structures.

(a)        Repealed by Session Laws 2013-185, s. 2, effective October 1, 2013, and applicable to applications received on or after that date.

(b)        Any person that proposes to construct a new wireless support structure or substantially modify a wireless support structure within the planning and land-use jurisdiction of a county must do both of the following:

(1)        Submit a completed application with the necessary copies and attachments to the appropriate planning authority.

(2)        Comply with any local ordinances concerning land use and any applicable permitting processes.

(c)        A county's review of an application for the placement or construction of a new wireless support structure or substantial modification of a wireless support structure shall only address public safety, land development, or zoning issues. In reviewing an application, the county may not require information on or evaluate an applicant's business decisions about its designed service, customer demand for its service, or quality of its service to or from a particular area or site. A county may not require information that concerns the specific need for the wireless support structure, including if the service to be provided from the wireless support structure is to add additional wireless coverage or additional wireless capacity. A county may not require proprietary, confidential, or other business information to justify the need for the new wireless support structure, including propagation maps and telecommunication traffic studies. In reviewing an application the county may review the following:

(1)        Applicable public safety, land use, or zoning issues addressed in its adopted regulations, including aesthetics, landscaping, land-use based location priorities, structural design, setbacks, and fall zones.

(2)        Information or materials directly related to an identified public safety, land development or zoning issue including evidence that no existing or previously approved wireless support structure can reasonably be used for the wireless facility placement instead of the construction of a new wireless support structure, that residential, historic, and designated scenic areas cannot be served from outside the area, or that the proposed height of a new wireless support structure or initial wireless facility placement or a proposed height increase of a substantially modified wireless support structure, or replacement wireless support structure or collocation is necessary to provide the applicant's designed service.

(3)        A county may require applicants for new wireless facilities to evaluate the reasonable feasibility of collocating new antennas and equipment on an existing wireless support structure or structures within the applicant's search ring. Collocation on an existing wireless support structure is not reasonably feasible if collocation is technically or commercially impractical or the owner of the existing wireless support structure is unwilling to enter into a contract for such use at fair market value. Counties may require information necessary to determine whether collocation on existing wireless support structures is reasonably feasible.

(d)       Repealed by Session Laws 2013-185, s. 2, effective October 1, 2013, and applicable to applications received on or after that date.

(e)        The county shall issue a written decision approving or denying an application under this section within a reasonable period of time consistent with the issuance of other land-use permits in the case of other applications, each as measured from the time the application is deemed complete.

(f)        A county may fix and charge an application fee, consulting fee, or other fee associated with the submission, review, processing, and approval of an application to site new wireless support structures or to substantially modify wireless support structures or wireless facilities that is based on the costs of the services provided and does not exceed what is usual and customary for such services. Any charges or fees assessed by a county on account of an outside consultant shall be fixed in advance and incorporated into a permit or application fee and shall be based on the reasonable costs to be incurred by the county in connection with the regulatory review authorized under this section. The foregoing does not prohibit a county from imposing additional reasonable and cost based fees for costs incurred should an applicant amend its application. On request, the amount of the consultant charges incorporated into the permit or application fee shall be separately identified and disclosed to the applicant. The fee imposed by a county for review of the application may not be used for either of the following:

(1)        Travel time or expenses, meals, or overnight accommodations incurred in the review of an application by a consultant or other third party.

(2)        Reimbursements for a consultant or other third party based on a contingent fee basis or a results-based arrangement.

(g)        The county may condition approval of an application for a new wireless support structure on the provision of documentation prior to the issuance of a building permit establishing the existence of one or more parties, including the owner of the wireless support structure, who intend to locate wireless facilities on the wireless support structure. A county shall not deny an initial land-use or zoning permit based on such documentation. A county may condition a permit on a requirement to construct facilities within a reasonable period of time, which shall be no less than 24 months.

(h)        The county may not require the placement of wireless support structures or wireless facilities on county owned or leased property, but may develop a process to encourage the placement of wireless support structures or facilities on county owned or leased property, including an expedited approval process.

(i)         This section shall not be construed to limit the provisions or requirements of any historic district or landmark regulation adopted pursuant to Part 3C of this Article.  (2007-526, s. 2; 2013-185, s. 2.)

 

§ 153A-349.53.  Collocation and eligible facilities requests of wireless support structures.

(a)        Pursuant to section 6409 of the federal Middle Class Tax Relief and Job Creation Act of 2012, 47 U.S.C. § 1455(a), a county may not deny and shall approve any eligible facilities request as provided in this section. Nothing in this Part requires an application and approval for routine maintenance or limits the performance of routine maintenance on wireless support structures and facilities, including in-kind replacement of wireless facilities. Routine maintenance includes activities associated with regular and general upkeep of transmission equipment, including the replacement of existing wireless facilities with facilities of the same size. A county may require an application for collocation or an eligible facilities request.

(a1)      A collocation or eligible facilities request application is deemed complete unless the county provides notice that the application is incomplete in writing to the applicant within 45 days of submission or within some other mutually agreed upon time frame. The notice shall identify the deficiencies in the application which, if cured, would make the application complete. A county may deem an application incomplete if there is insufficient evidence provided to show that the proposed collocation or eligible facilities request will comply with federal, State, and local safety requirements. A county may not deem an application incomplete for any issue not directly related to the actual content of the application and subject matter of the collocation or eligible facilities request. An application is deemed complete on resubmission if the additional materials cure the deficiencies indicated.

(a2)      The county shall issue a written decision approving an eligible facilities request application within 45 days of such application being deemed complete. For a collocation application that is not an eligible facilities request, the county shall issue its written decision to approve or deny the application within 45 days of the application being deemed complete.

(a3)      A county may impose a fee not to exceed one thousand dollars ($1,000) for technical consultation and the review of a collocation or eligible facilities request application. The fee must be based on the actual, direct, and reasonable administrative costs incurred for the review, processing, and approval of a collocation application. A county may engage a third-party consultant for technical consultation and the review of a collocation or eligible facilities request application. The fee imposed by a county for the review of the application may not be used for either of the following:

(1)        Travel expenses incurred in a third party's review of a collocation application.

(2)        Reimbursement for a consultant or other third party based on a contingent fee basis or results-based arrangement.

(b),       (c) Repealed by Session Laws 2013-185, s. 2, effective October 1, 2013, and applicable to applications received on or after that date.  (2007-526, s. 2; 2013-185, s. 2.)

 

Part 3C. Internet Access Service Grants.

§ 153A-349.60.  Authorization to provide grants.

(a)        A county may provide grants to unaffiliated qualified private providers of highspeed Internet access service, as that term is defined in G.S. 160A-340(4), for the purpose of expanding service in unserved areas for economic development in the county. The grants shall be awarded on a technology neutral basis, shall be open to qualified applicants, and may require matching funds by the private provider. A county shall seek and consider request for proposals from qualified private providers within the county prior to awarding a broadband grant and shall use reasonable means to ensure that potential applicants are made aware of the grant, including, at a minimum, compliance with the notice procedures set forth in G.S. 160A-340.6(c). The county shall use only unrestricted general fund revenue for the grants. For the purposes of this section, a qualified private provider is a private provider of high-speed Internet access service in the State prior to the issuance of the grant proposal.

(b)        Nothing in this section authorizes a county to provide highspeed Internet broadband service.  (2011-163, ss. 1, 2; 2012-86, s. 3.)

 

Part 4. Building Inspection.

§ 153A-350.  "Building" defined.

As used in this Part, the words "building" or "buildings" include other structures. (1973, c. 822, s. 1.)

 

§ 153A-350.1.  Tribal lands.

As used in this Part, the term:

(1)        "Board of commissioners" includes the Tribal Council of such tribe.

(2)        "County" or "counties" also means a federally recognized Indian Tribe, and as to such tribe includes lands held in trust for the tribe. (1999-78, s. 1.)

 

§ 153A-351.  Inspection department; certification of electrical inspectors.

(a)        A county may create an inspection department, consisting of one or more inspectors who may be given the titles of building inspector, electrical inspector, plumbing inspector, housing inspector, zoning inspector, heating and air-conditioning inspector, fire prevention inspector, deputy or assistant inspector, or any other title that is generally descriptive of the duties assigned.  The department may be headed by a superintendent or director of inspections.

(a1)      Every county shall perform the duties and responsibilities set forth in G.S. 153A-352 either by:

(1)        Creating its own inspection department;

(2)        Creating a joint inspection department in cooperation with one or more other units of local government, pursuant to G.S. 153A-353 or Part 1 of Article 20 of Chapter 160A; or,

(3)        Contracting with another unit of local government for the provision of inspection services pursuant to Part 1 of Article 20 of Chapter 160A.

Such action shall be taken no later than the applicable date in the schedule below, according to the county's population as published in the 1970 United States Census:

Counties over 75,000 population - July 1, 1979

Counties between 50,001 and 75,000 - July 1, 1981

Counties between 25,001 and 50,000 - July 1, 1983

Counties 25,000 and under - July 1, 1985.

In the event that any county shall fail to provide inspection services by the date specified above or shall cease to provide such services at any time thereafter, the Commissioner of Insurance shall arrange for the provision of such services, either through personnel employed by his Department or through an arrangement with other units of government.  In either event, the Commissioner shall have and may exercise within the county's jurisdiction all powers made available to the board of county commissioners with respect to building inspection under Part 4 of Article 18 of this Chapter and Part 1 of Article 20 of Chapter 160A.  Whenever the Commissioner has intervened in this manner, the county may assume provision of inspection services only after giving the Commissioner two years' written notice of its intention to  do so; provided, however, that the Commissioner may waive this requirement or permit assumption at an earlier date if he finds that such earlier assumption will not unduly interfere with arrangements he has made for the provision of those services.

(b)        No person may perform electrical inspections pursuant to this Part unless he has been certified as qualified by the Commissioner of Insurance.  To be certified a person must pass a written examination based on the electrical regulations included in the latest edition of the State Building Code as filed with the Secretary of State.  The examination shall be under the supervision of and conducted according to rules and regulations prescribed by the Chief State Electrical Inspector or Engineer of the State Department of Insurance and the Board of Examiners of Electrical Contractors.  It shall be held quarterly, in Raleigh or any other place designated by the Chief State Electrical Inspector or Engineer.

The rules and regulations may provide for the certification of class I, class II, and class III inspectors, according to the results of the examination.  The examination shall be based on the type and character of electrical installations being made in the territory in which the applicant wishes to serve as an electrical inspector.  A class I inspector may serve anywhere in the State, but class II and class III inspectors shall be limited to service in the territory for  which they have qualified.

The Commissioner of Insurance shall issue a certificate to each person who passes the examination, approving the person for service in a designated territory.  To remain valid, a certificate must be renewed each January by payment of an annual renewal fee of one dollar ($1.00).  The examination fee shall be five dollars ($5.00).

If the person appointed by a county as electrical inspector fails to pass the examination, the county shall continue to make appointments until an appointee has passed the examination.  For the interim the Commissioner of Insurance may authorize the county to use a temporary inspector.

The provisions of this subsection shall become void and ineffective on such date as the North Carolina Code Officials Qualification Board certifies to the Secretary of State that it has placed in effect a certification system for electrical inspectors pursuant to its authority granted by Article 9C of Chapter 143 of the General Statutes. (1937, c. 57; 1941, c. 105; 1947, c. 719; 1951, c. 651; 1953, c. 984; 1955, cc. 144, 942, 1171; 1957, cc. 415, 456, 1286, 1294; 1959, cc. 399, 940, 1031; 1961, cc. 763, 884, 1036; 1963, cc. 639, 868; 1965, cc. 243, 371, 453, 494, 846; 1967, cc. 45, 73, 113; c. 495, ss. 1, 3; 1969, cc. 675, 918; c. 1003, s. 7; c. 1010, s. 4; c. 1064, ss. 1, 4, 5; c. 1066, s. 1; 1973, c. 822, s. 1; 1977, c. 531, ss. 2, 3; 1991, c. 720, s. 77.)

 

§ 153A-351.1.  Qualifications of inspectors.

On and after the applicable date set forth in the schedule in G.S. 153A-351, no county shall employ an inspector to enforce the State Building Code as a member of a county or joint inspection department who does not have one of the following types of certificates issued by the North Carolina Code Officials Qualification Board attesting to his qualifications to hold such position: (i) a probationary certificate, valid for one year only; (ii) a standard certificate; or (iii) a limited certificate, which shall be valid only as an authorization for him to continue in the position held on the date specified in G.S. 143-151.10(c) and which shall become invalid if he does not successfully complete in-service training prescribed by the Qualification Board within the period specified in G.S. 143-151.10(c). An inspector holding one of the above certificates can be promoted to a position requiring a higher level certificate only upon  issuance by the Board of a standard certificate or probationary certificate appropriate for such new position. (1977, c. 531, s. 4.)

 

§ 153A-352.  Duties and responsibilities.

(a)        The duties and responsibilities of an inspection department and of the inspectors in it are to enforce within the county's territorial jurisdiction State and local laws and local ordinances and regulations relating to:

(1)        The construction of buildings;

(2)        The installation of such facilities as plumbing systems, electrical systems, heating systems, refrigeration systems, and air-conditioning systems;

(3)        The maintenance of buildings in a safe, sanitary, and healthful condition;

(4)        Other matters that may be specified by the board of commissioners.

(a1)      The duties and responsibilities set forth in subsection (a) of this section include receiving applications for permits and issuing or denying permits, making necessary inspections in a timely manner, issuing or denying certificates of compliance, issuing orders to correct violations, bringing judicial actions against actual or threatened violations, keeping adequate records, and taking any other actions that may be required to adequately enforce the laws and ordinances and regulations. The board of commissioners may enact reasonable and appropriate provisions governing the enforcement of the laws and ordinances and regulations.

(b)        Except as provided in G.S. 153A-364, a county may not adopt a local ordinance or resolution or any other policy that requires regular, routine inspections of buildings or structures constructed in compliance with the North Carolina Residential Code for One- and Two-Family Dwellings in addition to the specific inspections required by the North Carolina Building Code without first obtaining approval from the North Carolina Building Code Council. The North Carolina Building Code Council shall review all applications for additional inspections requested by a county and shall, in a reasonable manner, approve or disapprove the additional inspections. This subsection does not limit the authority of the county to require inspections upon unforeseen or unique circumstances that require immediate action. In performing the specific inspections required by the North Carolina Building Code, the inspector shall conduct all inspections requested by the permit holder for each scheduled inspection visit. For each requested inspection, the inspector shall inform the permit holder of instances in which the work inspected is incomplete or otherwise fails to meet the requirements of the North Carolina Residential Code for One- and Two-Family Dwellings.

(c)        Notwithstanding the requirements of this Article, a county shall accept and approve, without further responsibility to inspect, a design or other proposal for a component or element in the construction of buildings from a licensed architect or licensed engineer provided all of the following apply:

(1)        The submission is completed under valid seal of the licensed architect or licensed engineer.

(2)        Field inspection of the installation or completion of construction component or element of the building is performed by that licensed architect or licensed engineer.

(3)        That licensed architect or licensed engineer provides the county with a signed written document stating the component or element of the building so inspected is in compliance with the North Carolina State Building Code or the North Carolina Residential Code for One- and Two-Family Dwellings.

(d)       Upon the acceptance and approval of a signed written document by the county as required under subsection (c) of this section, the county, its inspection department, and the inspectors shall be discharged and released from any duties and responsibilities imposed by this Article with respect to the component or element in the construction of the building for which the signed written document was submitted.  (1937, c. 57; 1941, c. 105; 1947, c. 719; 1951, c. 651; 1953, c. 984; 1955, cc. 144, 942, 1171; 1957, cc. 415, 456, 1286, 1294; 1959, cc. 399, 940, 1031; 1961, cc. 763, 884, 1036; 1963, cc. 639, 868; 1965, cc. 243, 371, 453, 494, 846; 1967, cc. 45, 73, 113; c. 495, ss. 1, 3; 1969, cc. 675, 918; c. 1003, s. 7; c. 1010, s. 4; c. 1064, ss. 1, 4, 5; c. 1066, s. 1; 1973, c. 822, s. 1; 2013-118, s. 1(a); 2015-145, ss. 8.1, 9(a).)

 

§ 153A-353.  Joint inspection department; other arrangements.

A county may enter into and carry out contracts with one or more other counties or cities under which the parties agree to create and support a joint inspection department for enforcing those State and local laws and local ordinances and regulations specified in the agreement. The governing bodies of the contracting units may make any necessary appropriations for this purpose.

In lieu of a joint inspection department, a county may designate an inspector from another county or from a city to serve as a member of the county inspection department, with the approval of the governing body of the other county or city. A county may also contract with an individual who is not a city or county employee but who holds one of the applicable certificates as provided in G.S. 153A-351.1 or G.S. 160A-411.1 or with the employer of an individual who holds one of the applicable certificates as provided in G.S. 153A-351.1 or G.S. 160A-411.1. The inspector, if designated from another county or city under this section, while exercising the duties of the position, is a county employee. The county shall have the same potential liability, if any, for inspections conducted by an individual who is not an employee of the county as it does for an individual who is an employee of the county. The company or individual with whom the county contracts shall have errors and omissions and other insurance coverage acceptable to the county. (1937, c. 57; 1941, c. 105; 1947, c. 719; 1951, c. 651; 1959, c. 940; 1963, c. 639; 1965, c. 371; 1967, c. 495, s. 1; 1969, c. 918; c. 1010, s. 4; c. 1064, ss. 1, 5; c. 1066, s. 1; 1973, c. 822, s. 1; 1993, c. 232, s. 1; 1999-372, s. 1; 2001-278, s. 1.)

 

§ 153A-354.  Financial support.

A county may appropriate any available funds for the support of its inspection department. It may provide for paying inspectors fixed salaries, or it may reimburse them for their services by paying over part or all of any fees collected. It may fix reasonable fees for issuing permits, for inspections, and for other services of the inspection department. All fees collected under the authority set forth in this section shall be used for support of the administration and activities of the inspection department and for no other purpose.  (1937, c. 57; 1941, c. 105; 1947, c. 719; 1951, c. 651; 1953, c. 984; 1955, cc. 144, 942, 1171; 1957, cc. 415, 456, 1286, 1294; 1959, cc. 399, 940, 1031; 1961, cc. 763, 884, 1036; 1963, cc. 639, 868; 1965, cc. 243, 371, 453, 494, 846; 1967, cc. 45, 73, 113; c. 495, ss. 1, 3; 1969, cc. 675, 918; c. 1003, s. 7; c. 1010, s. 4; c. 1064, ss. 1, 4, 5; c. 1066, s. 1; 1973, c. 822, s. 1; 2015-145, s. 7.1.)

 

§ 153A-355.  Conflicts of interest.

Unless he or she is the owner of the building, no member of an inspection department shall be financially interested or employed by a business that is financially interested in furnishing labor, material, or appliances for the construction, alteration, or maintenance of any building within the county's territorial jurisdiction or any part or system thereof, or in making plans or specifications therefor. No member of any inspection department or other individual or an employee of a company contracting with a county to conduct inspections may engage in any work that is inconsistent with his or her duties or with the interest of the county, as determined by the county. The county must find a conflict of interest if any of the following is the case:

(1)        If the individual, company, or employee of a company contracting to perform inspections for the county has worked for the owner, developer, contractor, or project manager of the project to be inspected within the last two years.

(2)        If the individual, company, or employee of a company contracting to perform inspections for the county is closely related to the owner, developer, contractor, or project manager of the project to be inspected.

(3)        If the individual, company, or employee of a company contracting to perform inspections for the county has a financial or business interest in the project to be inspected. (1937, c. 57; 1941, c. 105; 1947, c. 719; 1951, c. 651; 1953, c. 984; 1955, cc. 144, 942, 1171; 1957, cc. 415, 456, 1286, 1294; 1959, cc. 399, 1031; 1961, cc. 763, 884, 1036; 1963, c. 868; 1965, cc. 243, 453, 494, 846; 1967, cc. 45, 73, 113; c. 495, s. 3; 1969, cc. 675, 918; c. 1003, s. 7; c. 1064, ss. 1, 4; c. 1066, s. 1; 1973, c. 822, s. 1; 1993, c. 232, s. 2; 1999-372, s. 2.)

 

§ 153A-356.  Failure to perform duties.

(a)        If a member of an inspection department willfully fails to perform the duties required of him by law, or willfully improperly issues a permit, or gives a certificate of compliance without first making the inspections required by law, or willfully improperly gives a certificate of compliance, he is guilty of a Class 1 misdemeanor.

(b)        A member of the inspection department shall not be in violation of this section when the county, its inspection department, or one of the inspectors accepted a signed written document of compliance with the North Carolina State Building Code or the North Carolina Residential Code for One- and Two-Family Dwellings from a licensed architect or licensed engineer in accordance with G.S. 153A-352(c).  (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1993, c. 539, s. 1064; 1994, Ex. Sess., c. 24, s. 14(c); 2015-145, s. 9(b).)

 

§ 153A-357.  Permits.

(a)        Except as provided in subsection (a2) of this section, no person may commence or proceed with any of the following without first securing from the inspection department with jurisdiction over the site of the work each permit required by the State Building Code and any other State or local law or local ordinance or regulation applicable to the work:

(1)        The construction, reconstruction, alteration, repair, movement to another site, removal, or demolition of any building.

(2)        The installation, extension, or general repair of any plumbing system except that in any one- or two-family dwelling unit a permit shall not be required for the connection of a water heater that is being replaced, provided that the work is performed by a person licensed under G.S. 87-21, who personally examines the work at completion and ensures that a leak test has been performed on the gas piping, and provided the energy use rate or thermal input is not greater than that of the water heater which is being replaced, there is no change in fuel, energy source, location, capacity, or routing or sizing of venting and piping, and the replacement is installed in accordance with the current edition of the State Building Code.

(3)        The installation, extension, alteration, or general repair of any heating or cooling equipment system.

(4)        The installation, extension, alteration, or general repair of any electrical wiring, devices, appliances, or equipment except that in any one- or two-family dwelling unit a permit shall not be required for repair or replacement of electrical lighting fixtures or devices, such as receptacles and lighting switches, or for the connection of an existing branch circuit to an electric water heater that is being replaced, provided that all of the following requirements are met:

a.         With respect to electric water heaters, the replacement water heater is placed in the same location and is of the same or less capacity and electrical rating as the original.

b.         With respect to electrical lighting fixtures and devices, the replacement is with a fixture or device having the same voltage and the same or less amperage.

c.         The work is performed by a person licensed under G.S. 87-43.

d.         The repair or replacement installation meets the current edition of the State Building Code, including the State Electrical Code.

However, a permit is not required for the installation, maintenance, or replacement of any load control device or equipment by an electric power supplier, as defined in G.S. 62-133.8, or an electrical contractor contracted by the electric power supplier, so long as the work is subject to supervision by an electrical contractor licensed under Article 4 of Chapter 87 of the General Statutes. The electric power supplier shall provide such installation, maintenance, or replacement in accordance with (i) an activity or program ordered, authorized, or approved by the North Carolina Utilities Commission pursuant to G.S. 62-133.8 or G.S. 62-133.9 or (ii) a similar program undertaken by a municipal electric service provider, whether the installation, modification, or replacement is made before or after the point of delivery of electric service to the customer. The exemption under this subdivision applies to all existing installations.

(a1)      A permit shall be in writing and shall contain a provision that the work done shall comply with the State Building Code and all other applicable State and local laws and local ordinances and regulations. Nothing in this section shall require a county to review and approve residential building plans submitted to the county pursuant to Section R-110 of Volume VII of the North Carolina State Building Code; provided that the county may review and approve such residential building plans as it deems necessary. No permit may be issued unless the plans and specifications are identified by the name and address of the author thereof; and if the General Statutes of North Carolina require that plans for certain types of work be prepared only by a licensed architect or licensed engineer, no permit may be issued unless the plans and specifications bear the North Carolina seal of a licensed architect or of a licensed engineer. If a provision of the General Statutes of North Carolina or of any ordinance requires that work be done by a licensed specialty contractor of any kind, no permit for the work may be issued unless the work is to be performed by such a duly licensed contractor.

(a2)      No permit issued under Articles 9 or 9C of G.S. Chapter 143 shall be required for any construction, installation, repair, replacement, or alteration performed in accordance with the current edition of the North Carolina State Building Code and costing fifteen thousand dollars ($15,000) or less in any single-family residence or farm building unless the work involves any of the following:

(1)        The addition, repair or replacement of load bearing structures. However, no permit is required for replacements of windows, doors, exterior siding, or the pickets, railings, stair treads, and decking of porches and exterior decks.

(2)        The addition or change in the design of plumbing. However, no permit is required for replacements otherwise meeting the requirements of this subsection that do not change size or capacity.

(3)        The addition, replacement or change in the design of heating, air conditioning, or electrical wiring, devices, appliances, or equipment, other than like-kind replacement of electrical devices and lighting fixtures.

(4)        The use of materials not permitted by the North Carolina Residential Code for One- and Two-Family Dwellings.

(5)        The addition (excluding replacement) of roofing.

(a3)      A county shall not require more than one permit for the complete installation or replacement of any natural gas, propane gas, or electrical appliance on an existing structure when the installation or replacement is performed by a person licensed under G.S. 87-21 or G.S. 87-43. The cost of the permit for such work shall not exceed the cost of any one individual trade permit issued by that county, nor shall the county increase the costs of any fees to offset the loss of revenue caused by this provision.

(b)        No permit shall be issued pursuant to subsection (a) for any land-disturbing activity, as defined in G.S. 113A-52(6), for any activity covered by G.S. 113A-57, unless an erosion and sedimentation control plan has been approved by the Sedimentation Pollution Control Commission pursuant to G.S. 113A-54(d)(4) or by a local government pursuant to G.S. 113A-61 for the site of the activity or a tract of land including the site of the activity.

(c)       (1)        A county may by ordinance provide that a permit may not be issued under subsection (a) of this section to a person who owes delinquent property taxes, determined under G.S. 105-360, on property owned by the person. Such ordinance may provide that a building permit may be issued to a person protesting the assessment or collection of property taxes.

(2)        This subsection applies to Alexander, Alleghany, Anson, Bertie, Catawba, Chowan, Currituck, Davie, Gates, Greene, Lenoir, Lincoln, Iredell, Sampson, Stokes, Surry, Tyrrell, Wayne, and Yadkin Counties only.

(d)       Repealed by Session Laws 2014-115, s. 15(a), effective August 11, 2014.

(e)        (Effective until July 1, 2017) No permit shall be issued pursuant to subdivision (1) of subsection (a) of this section where the cost of the work is thirty thousand dollars ($30,000) or more, other than for improvements to an existing single-family residential dwelling unit as defined in G.S. 87-15.5(7) that the owner occupies as a residence, or for the addition of an accessory building or accessory structure as defined in the North Carolina Uniform Residential Building Code, the use of which is incidental to that residential dwelling unit, unless the name, physical and mailing address, telephone number, facsimile number, and electronic mail address of the lien agent designated by the owner pursuant to G.S. 44A-11.1(a) is conspicuously set forth in the permit or in an attachment thereto. The building permit may contain the lien agent's electronic mail address. The lien agent information for each permit issued pursuant to this subsection shall be maintained by the inspection department in the same manner and in the same location in which it maintains its record of building permits issued.

(e)        (Effective July 1, 2017) No permit shall be issued pursuant to subdivision (1) of subsection (a) of this section where the cost of the work is thirty thousand dollars ($30,000) or more, other than for improvements to an existing single-family residential dwelling unit as defined in G.S. 87-15.5(7) that the owner occupies as a residence, or for the addition of an accessory building or accessory structure as defined in the North Carolina Uniform Residential Building Code, the use of which is incidental to that residential dwelling unit, unless the name, physical and mailing address, telephone number, facsimile number, and electronic mail address of the lien agent designated by the owner pursuant to G.S. 44A-11.1(a) is conspicuously set forth in the permit or in an attachment thereto. The building permit may contain the lien agent's electronic mail address. The lien agent information for each permit issued pursuant to this subsection shall be maintained by the inspection department in the same manner and in the same location in which it maintains its record of building permits issued. Where the improvements to a real property leasehold are limited to the purchase, transportation, and setup of a manufactured home, as defined in G.S. 143-143.9(6), for which there is a current certificate of title, the purchase price of the manufactured home shall be excluded in determining whether the cost of the work is thirty thousand dollars ($30,000) or more.

(f)        No county may withhold issuing a building permit or certificate of occupancy that otherwise would be eligible to be issued under this section to compel, with respect to another property or parcel, completion of work for a separate permit or compliance with land use regulations under this Article unless otherwise authorized by law or unless the county reasonably determines the existence of a public safety issue directly related to the issuance of a building permit or certificate of occupancy.

(g)        Violation of this section constitutes a Class 1 misdemeanor.  (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1981, c. 677, s. 2; 1983, c. 377, s. 2; c. 614, s. 2; 1987 (Reg. Sess., 1988), c. 1000, s. 1; 1993, c. 539, s. 1065; 1994, Ex. Sess., c. 24, s. 14(c); 1993 (Reg. Sess., 1994), c. 741, s. 1; 2002-165, s. 2.19; 2005-433, s. 3; 2006-150, s. 2; 2007-58, s. 1; 2008-198, s. 8(c); 2009-117, s. 1; 2009-532, s. 2; 2010-30, s. 3; 2012-23, s. 2; 2012-158, s. 6; 2013-58, s. 2; 2013-117, s. 6; 2013-160, s. 1; 2014-115, s. 15(a); 2015-145, s. 4.2(a), (b); 2015-187, s. 2(b); 2016-59, s. 8; 2016-113, s. 13(b).)

 

§ 153A-358.  Time limitations on validity of permits.

A permit issued pursuant to G.S. 153A-357 expires six months, or any lesser time fixed by ordinance of the county, after the date of issuance if the work authorized by the permit has not commenced. If after commencement the work is discontinued for a period of 12 months, the permit therefor immediately expires. No work authorized by a permit that has expired may thereafter be performed until a new permit has been secured. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-359.  Changes in work.

After a permit has been issued, no change or deviation from the terms of the application, the plans and specifications, or the permit, except if the change or deviation is clearly permissible under the State Building Code, may be made until specific written approval of the proposed change or deviation has been obtained from the inspection department. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-360.  Inspections of work in progress.

Subject to the limitation imposed by G.S. 153A-352(b), as the work pursuant to a permit progresses, local inspectors shall make as many inspections of the work as may be necessary to satisfy them that it is being done according to the provisions of the applicable State and local laws and local ordinances and regulations and of the terms of the permit. In exercising this power, each member of the inspection department has a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action. If a permit has been obtained by an owner exempt from licensure under G.S. 87-1(b)(2), no inspection shall be conducted without the owner being personally present, unless the plans for the building were drawn and sealed by an architect licensed pursuant to Chapter 83A of the General Statutes.  (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 2011-376, s. 3; 2015-145, s. 1(a).)

 

§ 153A-361.  Stop orders.

Whenever a building or part thereof is being demolished, constructed, reconstructed, altered, or repaired in a hazardous manner, or in substantial violation of a State or local building law or local building ordinance or regulation, or in a manner that endangers life or property, the appropriate inspector may order the specific part of the work that is in violation or that presents such a hazard to be immediately stopped.  The stop order shall be in writing and directed to the person doing the work, and shall state the specific work to be stopped, the specific reasons for the stoppage, and the conditions under which the work may be resumed.  The owner or builder may appeal from a stop order involving alleged violation of the State Building Code or any approved local modification thereof to the North Carolina Commissioner of Insurance or his designee within five days after the day the order is issued.  The owner or builder shall give to the Commissioner of Insurance or his designee written notice of appeal, with a copy to the local inspector.  The Commissioner or his designee shall promptly conduct an investigation and the appellant and the inspector shall be permitted to submit relevant evidence.  The Commissioner or his designee shall as expeditiously as possible provide a written statement of the decision setting forth the facts found, the decision reached, and the reasons for the decision.  Pending the ruling by the Commissioner of Insurance or his designee on an appeal, no further work may take place in violation of a stop order.  In the event of dissatisfaction with the decision, the person affected shall have the options of:

(1)        Appealing to the Building Code Council, or

(2)        Appealing to the Superior Court as provided in G.S.143-141.

Violation of a stop order constitutes a Class 1 misdemeanor. (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1983, c. 377, s. 4; 1989, c. 681, s. 5; 1993, c. 539, s. 1066; 1994, Ex. Sess., c. 24, s. 14(c).)

 

§ 153A-362.  Revocation of permits.

The appropriate inspector may revoke and require the return of any permit by giving written notice to the permit holder, stating the reason for the revocation. Permits shall be revoked for any substantial departure from the approved application or plans and specifications, for refusal or failure to comply with the requirements of any applicable State or local laws or local ordinances or regulations, or for false statements or misrepresentations made in securing the permit. A permit mistakenly issued in violation of an applicable State or local law or local ordinance or regulation also may be revoked. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-363.  Certificates of compliance.

At the conclusion of all work done under a permit, the appropriate inspector shall make a final inspection.  If he finds that the completed work complies with all applicable State and local laws and local ordinances and regulations and with the terms of the permit, he shall issue a certificate of compliance.  No new building or part thereof may be occupied, no addition or enlargement of an existing building may be occupied, and no existing building that has been altered or removed may be occupied until the inspection department has issued a certificate of compliance.  A temporary certificate of compliance may be issued permitting occupancy for a stated period of specified portions of the building that the inspector finds may safely be occupied before completion of the entire building.  Violation of this section constitutes a Class 1 misdemeanor. (1973, c. 822, s. 1; 1993, c. 539, s. 1067; 1994, Ex. Sess., c. 24, s. 14(c).)

 

§ 153A-364.  Periodic inspections for hazardous or unlawful conditions.

(a)        The inspection department may make periodic inspections, subject to the board of commissioners' directions, for unsafe, unsanitary, or otherwise hazardous and unlawful conditions in buildings or structures within its territorial jurisdiction. However, when the inspection department determines that a safety hazard exists in one of the dwelling units within a multifamily building, which in the opinion of the inspector poses an immediate threat to the occupant, the inspection department may inspect, in the absence of a specific complaint and actual knowledge of the unsafe condition, additional dwelling units in the multifamily building to determine if that same safety hazard exists. Except as provided in subsection (b) of this section, the inspection department may make periodic inspections only when there is reasonable cause to believe that unsafe, unsanitary, or otherwise hazardous or unlawful conditions may exist in a residential building or structure. For purposes of this section, the term "reasonable cause" means any of the following: (i) the property has a history of more than four verified violations of the housing ordinances or codes within a rolling 12-month period; (ii) there has been a complaint that substandard conditions exist within the building or there has been a request that the building be inspected; (iii) the inspection department has actual knowledge of an unsafe condition within the building; or (iv) violations of the local ordinances or codes are visible from the outside of the property. In conducting inspections authorized under this section, the inspection department shall not discriminate between single-family and multifamily buildings or between owner-occupied and tenant-occupied buildings. In exercising these powers, each member of the inspection department has a right, upon presentation of proper credentials, to enter on any premises within the territorial jurisdiction of the department at any reasonable hour for the purposes of inspection or other enforcement action. Nothing in this section shall be construed to prohibit periodic inspections in accordance with State fire prevention code or as otherwise required by State law.

(b)        A county may require periodic inspections as part of a targeted effort to respond to blighted or potentially blighted conditions within a geographic area that has been designated by the county commissioners. However, the total aggregate of targeted areas in the county at any one time shall not be greater than one square mile or five percent (5%) of the area within the county, whichever is greater. A targeted area designated by the county shall reflect the county's stated neighborhood revitalization strategy and shall consist of property that meets the definition of a "blighted area" or "blighted parcel" as those terms are defined in G.S. 160A-503(2) and G.S. 160A-503(2a), respectively, except that for purposes of this subsection the planning commission is not required to make a determination as to the property. The county shall (i) provide notice to all owners and residents of properties in the affected area about the periodic inspections plan and information regarding a public hearing regarding the plan; (ii) hold a public hearing regarding the plan; and (iii) establish a plan to address the ability of low-income residential property owners to comply with minimum housing code standards. A residential building or structure that is subject to periodic inspections by the North Carolina Housing Finance Agency (hereinafter "Agency") shall not be subject to periodic inspections under this subsection if the Agency has issued a finding that the building or structure is in compliance with federal standards established by the United States Department of Housing and Urban Development to assess the physical condition of residential property. The owner or manager of a residential building or structure subject to periodic inspections by the Agency shall, within 10 days of receipt, submit to the inspection department a copy of the Compliance Results Letter issued by the Agency showing that the residential building or structure is in compliance with federal housing inspection standards. If the owner or manager fails to submit a copy of the Compliance Results Letter as provided in this subsection, the residential building or structure shall be subject to periodic inspections as provided in this subsection until the Compliance Results Letter is submitted to the inspection department.

(c)        In no event may a county do any of the following: (i) adopt or enforce any ordinance that would require any owner or manager of rental property to obtain any permit or permission from the county to lease or rent residential real property or to register rental property with the county, except for those individual rental units that have either more than four verified violations of housing ordinances or codes in a rolling 12-month period or two or more verified violations in a rolling 30-day period, or upon the property being identified within the top ten percent (10%) of properties with crime or disorder problems as set forth in a local ordinance; (ii) require that an owner or manager of residential rental property enroll or participate in any governmental program as a condition of obtaining a certificate of occupancy; (iii) levy a special fee or tax on residential rental property that is not also levied against other commercial and residential properties, unless expressly authorized by general law or applicable only to an individual rental unit or property described in clause (i) of this subsection and the fee does not exceed five hundred dollars ($500.00) in any 12-month period in which the unit or property is found to have verified violations; (iv) provide that any violation of a rental registration ordinance is punishable as a criminal offense; or (v) require any owner or manager of rental property to submit to an inspection before receiving any utility service provided by the city. For purposes of this section, the term "verified violation" means all of the following:

(1)        The aggregate of all violations of housing ordinances or codes found in an individual rental unit of residential real property during a 72-hour period.

(2)        Any violations that have not been corrected by the owner or manager within 21 days of receipt of written notice from the county of the violations. Should the same violation occur more than two times in a 12-month period, the owner or manager may not have the option of correcting the violation. If the housing ordinance or code provides that any form of prohibited tenant behavior constitutes a violation by the owner or manager of the rental property, it shall be deemed a correction of the tenant-related violation if the owner or manager, within 30 days of receipt of written notice of the tenant-related violation, brings a summary ejectment action to have the tenant evicted.

(d)       Repealed by Session Laws 2016-122, s. 1, effective January 1, 2017.

(e)        If a property is identified by the county as being in the top ten percent (10%) of properties with crime or disorder problems, the county shall notify the landlord of any crimes, disorders, or other violations that will be counted against the property to allow the landlord an opportunity to attempt to correct the problems. In addition, the county and the county sheriff's office shall assist the landlord in addressing any criminal activity, which may include testifying in court in a summary ejectment action or other matter to aid in evicting a tenant who has been charged with a crime. If the county or the county sheriff's office does not cooperate in evicting a tenant, the tenant's behavior or activity at issue shall not be counted as a crime or disorder problem as set forth in the local ordinance, and the property may not be included in the top ten percent (10%) of properties as a result of that tenant's behavior or activity.

(f)        If the county takes action against an individual rental unit under this section, the owner of the individual rental unit may appeal the decision to the housing appeals board or the zoning board of adjustment, if operating, or the planning board if created under G.S. 153A-321, or if neither is created, the governing board. The board shall fix a reasonable time for hearing appeals, shall give due notice to the owner of the individual rental unit, and shall render a decision within a reasonable time. The owner may appear in person or by agent or attorney. The board may reverse or affirm the action, wholly or partly, or may modify the action appealed from, and may make any decision and order that in the opinion of the board ought to be made in the matter.  (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 2011-281, s. 1; 2014-103, s. 13(a); 2016-122, s. 1.)

 

§ 153A-365.  Defects in buildings to be corrected.

If a local inspector finds any defect in a building, or finds that the building has not been constructed in accordance with the applicable State and local laws and local ordinances and regulations, or finds that a building because of its condition is dangerous or contains fire-hazardous conditions, he shall notify the owner or occupant of the building of its defects, hazardous conditions, or failure to comply with law. The owner and the occupant shall each immediately remedy the defects, hazardous conditions, or violations of law in the property each owns. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-366.  Unsafe buildings condemned.

The inspector shall condemn as unsafe each building that appears to him to be especially dangerous to life because of its liability to fire, bad conditions of walls, overloaded floors, defective construction, decay, unsafe wiring or heating system, inadequate means of egress, or other causes; and he shall affix a notice of the dangerous character of the building to a conspicuous place on its exterior wall. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-367.  Removing notice from condemned building.

If a person removes a notice that has been affixed to a building by a local inspector and that states the dangerous character of the building, he is guilty of a Class 1 misdemeanor. (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1993, c. 539, s. 1068; 1994, Ex. Sess., c. 24, s. 14(c).)

 

§ 153A-368.  Action in event of failure to take corrective action.

If the owner of a building that has been condemned as unsafe pursuant to G.S. 153A-366 fails to take prompt corrective action, the local inspector shall by certified or registered mail to his last known address or by personal service give him written notice:

(1)        That the building is in a condition that appears to constitute  a fire or safety hazard or to be dangerous to life, health, or other property;

(2)        That a hearing will be held before the inspector at a designated place and time, not later than 10 days after the date of the notice, at which time the owner is entitled to be heard in person or by counsel and to present arguments and evidence pertaining to the matter; and

(3)        That following the hearing, the inspector may issue any order to repair, close, vacate, or demolish the building that appears appropriate.

If the name or whereabouts of the owner cannot after due diligence be  discovered, the notice shall be considered properly and adequately served if a copy thereof is posted on the outside of the building in question at least 10 days before the day of the hearing and a notice of the hearing is published at least once not later than one week before the hearing. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-369.  Order to take corrective action.

If, upon a hearing held pursuant to G.S. 153A-368, the inspector finds that the building is in a condition that constitutes a fire or safety hazard or renders it dangerous to life, health, or other property, he shall issue a written order, directed to the owner of the building, requiring the owner to remedy the defective conditions by repairing, closing, vacating, or demolishing the building or taking other necessary steps, within such period, not less than 60 days, as the inspector may prescribe; provided, that where the inspector finds that there is imminent danger to life or other property, he may order that corrective action be taken in such lesser period as may be feasible. (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1979, c. 611, s. 5.)

 

§ 153A-370.  Appeal; finality of order not appealed.

An owner who has received an order under G.S. 153A-369 may appeal from the order to the board of commissioners by giving written notice of appeal to the inspector and to the clerk within 10 days following the day the order is issued. In the absence of an appeal, the order of the inspector is final. The board of commissioners shall hear any appeal within a reasonable time and may affirm, modify and affirm, or revoke the order. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-371.  Failure to comply with order.

If the owner of a building fails to comply with an order issued pursuant to G.S. 153A-369 from which no appeal has been taken, or fails to comply with an order of the board of commissioners following an appeal, he is guilty of a Class 1 misdemeanor. (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1993, c. 539, s. 1069; 1994, Ex. Sess., c. 24, s. 14(c).)

 

§ 153A-372.  Equitable enforcement.

Whenever a violation is denominated a misdemeanor under the provisions of this Part, the county, either in addition to or in lieu of other remedies, may initiate any appropriate action or proceeding to prevent, restrain, correct, or abate the violation or to prevent the occupancy of the building involved. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

§ 153A-372.1.  Ordinance authorized as to repair, closing, and demolition of nonresidential buildings or structures; order of public officer.

The provisions of G.S. 160A-439 shall apply to counties. (2007-414, s. 2.)

 

§ 153A-373.  Records and reports.

The inspection department shall keep complete, and accurate records in convenient form of each application received, each permit issued, each inspection and reinspection made, and each defect found, each certificate of compliance granted, and all other work and activities of the department. These records shall be kept in the manner and for the periods prescribed by the North Carolina Department of Natural and Cultural Resources. The department shall submit periodic reports to the board of commissioners and to the Commissioner of Insurance as the board or the Commissioner may require.  (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1983, c. 377, s. 6; 2015-241, s. 14.30(s).)

 

§ 153A-374.  Appeals.

Unless otherwise provided by law, any appeal from an order, decision, or determination of a member of a local inspection department pertaining to the State Building Code or any other State building law shall be taken to the Commissioner of Insurance or his designee or other official specified in G.S. 143-139, by filing a written notice with him and with the inspection department within 10 days after the day of the order, decision, or determination. Further appeals may be taken to the State Building Code Council or to the courts as provided by law. (1969, c. 1066, s. 1; 1973, c. 822, s. 1; 1989, c. 681, s. 7.)

 

§ 153A-375.  Establishment of fire limits.

A county may by ordinance establish and define fire limits in any area within the county and not within a city. The limits may include only business and industrial areas. Within any fire limits, no frame or wooden building or addition thereto may be erected, altered, repaired, or moved (either into the fire limits or from one place to another within the limits) except upon the permit of the inspection department and approval of the Commissioner of Insurance. The board of commissioners may make additional regulations necessary for the prevention, extinguishment, or mitigation of fires within the fire limits. (1969, c. 1066, s. 1; 1973, c. 822, s. 1.)

 

Part 5. Community Development.

§ 153A-376.  Community development programs and activities.

(a)        Any county is authorized to engage in, to accept federal and State grants and loans for, and to appropriate and expend funds for community development programs and activities. In undertaking community development programs and activities, in addition to other authority granted by law, a county may engage in the following activities:

(1)        Programs of assistance and financing of rehabilitation of private buildings principally for the benefit of low and moderate income persons, or for the restoration or preservation of older neighborhoods or properties, including direct repair, the making of grants or loans, the subsidization of interest payments on loans, and the guaranty of loans;

(2)        Programs concerned with employment, economic development, crime prevention, child care, health, drug abuse, education, and welfare needs of persons of low and moderate income.

(b)        Any board of county commissioners may exercise directly those powers granted by law to county redevelopment commissions and those powers granted by law to county housing authorities. Any board of county commissioners desiring to do so may delegate to redevelopment commission or to any housing authority the responsibility of undertaking or carrying out any specified community development activities. Any board of county commissioners and any municipal governing body may by agreement undertake or carry out for each other any specified community development activities. Any board of county commissioners may contract with any person, association, or corporation in undertaking any specified community development activities. Any county or city board of health, county board of social services, or county or city board of education, may by agreement undertake or carry out for any board of county commissioners any specified community development activities.

(c)        Any board of county commissioners undertaking community development programs or activities may create one or more advisory committees to advise it and to make recommendations concerning such programs or activities.

(d)       Any board of county commissioners proposing to undertake any loan guaranty or similar program for rehabilitation of private buildings is authorized to submit to its voters the question whether such program shall be undertaken, such referendum to be conducted pursuant to the general and local laws applicable to special elections in such county.

(e)        No state or local taxes shall be appropriated or expended by a county pursuant to this section for any purpose not expressly authorized by G.S. 153A-149, unless the same is first submitted to a vote of the people as therein provided.

(f)        All program income from Economic Development Grants from the Small Cities Community Development Block Grant Program may be retained by recipient "economically distressed counties", as defined in G.S. 143B-437.01 for the purposes of creating local economic development revolving loan funds. Such program income derived through the use by counties of Small Cities Community Development Block Grant money includes but is not limited to: (i) payment of principal and interest on loans made by the county using Community Development Block Grant Funds; (ii) proceeds from the lease or disposition of real property acquired with Community Development Block Grant Funds; and (iii) any late fees associated with loan or lease payments in (i) and (ii) above. The local economic development revolving loan fund set up by the county shall fund only those activities eligible under Title I of the federal Housing and Community Development Act of 1974, as amended (P.L. 93-383), and shall meet at least one of the three national objectives of the Housing and Community Development Act. Any expiration of G.S. 143B-437.01 or G.S. 105-129.3 shall not affect this subsection as to designations of economically distressed counties made prior to its expiration.

(g)        Any county may receive and dispense funds from the Community Development Block Grant Section 108 Loan Guarantee program, Subpart M, 24 CFR 570.700 et seq., either through application to the North Carolina Department of Commerce or directly from the federal government, in accordance with State and federal laws governing these funds. Any county that receives these funds directly from the federal government may pledge current and future CDBG funds for use as loan guarantees in accordance with State and federal laws governing these funds. A county may implement the receipt, dispensing, and pledging of CDBG funds under this subsection by borrowing CDBG funds and lending all or a portion of those funds to a third party in accordance with applicable laws governing the CDBG program.

Any county that has pledged current or future CDBG funds for use as loan guarantees prior to the enactment of this subsection is authorized to have taken such action. A pledge of future CDBG funds under this subsection is not a debt or liability of the State or any political subdivision of the State or a pledge of the faith and credit of the State or any political subdivision of the State. The pledging of future CDBG funds under this subsection does not directly, indirectly, or contingently obligate the State or any political subdivision of the State to levy or to pledge any taxes. (1975, c. 435, s. 2; c. 689, s. 2; 1987 (Reg. Sess., 1988), c. 992, s. 1; 1995, c. 310, s. 2; 1995 (Reg. Sess., 1996), c. 575, s. 2; 1996, 2nd Ex. Sess., c. 13, s. 3.8; 2006-259, s. 27(a).)

 

§ 153A-377.  Acquisition and disposition of property for redevelopment.

In addition to the powers granted by G.S. 153A-376, any county is authorized, either as a part of a community development program or independently thereof, and without the necessity of compliance with the Urban Redevelopment Law, to exercise the following powers:

(1)        To acquire, by voluntary purchase from the owner or owners, real property which is either:

a.         Blighted, deteriorated, deteriorating, undeveloped, or inappropriately developed from the standpoint of sound community development and growth;

b.         Appropriate for rehabilitation or conservation activities;

c.         Appropriate for housing construction of the economic development of the community; or

d.         Appropriate for the preservation or restoration of historic sites, the beautification of urban land, the conservation of open space, natural resources, and scenic areas, the provision of recreational opportunities, or the guidance of urban development;

(2)        To clear, demolish, remove, or rehabilitate buildings and improvements on land so acquired; and

(3)        To retain property so acquired for public purposes, or to dispose, through sale, lease, or otherwise, of any property so acquired to any person, firm, corporation, or governmental unit; provided, the disposition of such property shall be undertaken in accordance with the procedures of G.S. 153A-176, or the procedures of G.S. 160A-514, or any applicable local act modifying such procedures. (1977, c. 660, s. 2.)

 

§ 153A-378.  Low-and moderate-income housing programs.

In addition to the powers granted by G.S. 153A-376 and G.S. 153A-377, any county is authorized to exercise the following powers:

(1)        To engage in and to appropriate and expend funds for residential housing construction, new or rehabilitated, for sale or rental to persons and families of low and moderate income. Any board of commissioners may contract with any person, association, or corporation to implement the provisions of this subdivision.

(2)        To acquire real property by voluntary purchase from the owners to be developed by the county or to be used by the county to provide affordable housing to persons of low and moderate income.

(3)        Under procedures and standards established by the county, to convey property by private sale to any public or private entity that provides affordable housing to persons of low or moderate income. The county shall include as part of any such conveyance covenants or conditions that assure the property will be developed by the entity for sale or lease to persons of low or moderate income.

(4)        Under procedures and standards established by the county, to convey residential property by private sale to persons of low or moderate income in accordance with G.S. 160A-267 and any terms and conditions that the board of commissioners may determine. (1999-366, s. 2.)

 

§§ G.S. 153A-379 through 153A-390.  Reserved for future codification purposes.